Projects Conditionally Approved by the ICC and the NEDA Board,
As of 22 January 2001
| PROJECT TITLE | IMPLEMENTING AGENCY | FUNDING SOURCE | PROJECT COST (TPC, FC, LC) (in millions) |
ICC DATE OF APPROVAL |
NEDA BOARD DATE OF APPROVAL | PENDING DOCUMENTS | ISSUES/REMARKS |
| PART I. Proposed Projects
Category A |
|||||||
| 1. Cebu-Mactan Interconnection Project | NPC | Miyazawa Initiative |
P 1251 |
15-Oct-98 | 25-Nov-98 | ECC (or Certificate of Non-coverage) | Draft IEE report for completion upon submission of additional inputs from Design. Expected issuance of ECC is on December 2000. RDC endorsement secured (Resolution #111-1996 dated 13 Dec. 1996) |
| 2. Maritime Safety Improvement Project C | DOTC | 23rd YLP |
P 2470 |
19-Nov-98 | 25-Nov-98 | ECC for the Construction of the Support Base | DOTC informed the ICC Secretariat of problems regarding the Mactan Buoy Base. Preliminary survey for possible alternative sites ongoing. |
| 3. Manila-Clark Rapid Railway System (MCRRS) Project - Section I (Caloocan to Calumpit) | BCDA | Obuchi Fund |
$1,052.00 |
23-Sep-99 | 21-Oct-99 | ECCs | Valenzuela-Clark
Section: Review process for the ECC concluded. ECC ready for
signing.
Monumento-Valenzuela Section: Final EIS has been submitted to the DENR-EMB. Currently in the final stages of the review process. Issuance of ECC expected by February 2001. |
| 4. Hospital Equipment Assistance Program of DILG | DILG | Spain |
P 707.67 |
18-Feb-2000 | 2-Jun-2000 | DILG to submit: MOAs among the participating agencies/parties to include the ff. provisions: (1) LGUs to aalocate funds for O&M of equipment; (2) DILG to pull out equipment if LGUs cannot maintain it; (3) DILG to revalidate list of recepient LGUs if there will be changes in administration. | Awaiting signed CNC from DENR-EMB. RDC endorsement for 3 out of 21 LGUs have yet to be submitted. All 21 LGUs have submitted MOAs. |
| 5. Industrial Pollution Control Loan Project (IPCLP), Phase II | DBP | KfW |
P 2540 |
28-Mar-2000 | 2-Jun-2000 | Project Completion Report and Impact Assessment Report for Phase I | According to DBP, the DBP-IPCLP team will prepare a preliminary conclusion report on IPCLP I by the end of March 2001. Since the implementation of some projects will be finished by that time only, the evaluation of these will be included in the final report. The due date of the Final Completion Report as agreed with the KfW is on end June 2001. The project's Impact Assessment Report will be submitted on or before the end of December 2001. |
| 6. Help for Catubig Agricultural Advancement Project (HCAAP) | NIA | 24th YLP |
P 2188 |
17-May-2000 | 2-Jun-2000 | (1) ECC for new road construction between Catubig and Las Navas including bridge crossing Catubig River | NIA is coordinating the ECC for the project with the DPWH - Region VIII. First level scoping has been completed; 2nd level scoping is forthcoming. The EIS will be submitted to the DENR-EMB by end of November 2000. MOA among participating agencies that clearly delineates the responsibilities of each party has been submitted to the ICC Secretariat. Issued provisional certification conditional to submission of ECC, to facilitate loan negs with JBIC |
| 7. New Iloilo Airport Development Project | DOTC | Obuchi |
P 6186.58 |
28-Mar-2000 | 2-Jun-2000 | Signed MOA between DOF and DOTC that will turnover disposition of assets of existing Iloilo Airport to DOF. | Per DOTC, the Department is coordinating the required MOA with the DOF. A copy of the MOA was forwarded to the DOF for review. ICC Secretariat issued provisional certification dated 17 August 2000 to facilitate MB processing of loan for the project. |
| 8. Infrastructure Support for Rural Productivity Enhancement Sector | DA | ADB |
P 7066.8 |
3-Aug-2000 | 15-Aug-2000 | DA to coordinate the implementation of said project through an interagency mechanism | The DA submitted to the ICC Special Order #156 (9/14/00) establishing the coordination and management mechanism for the implementation of the INFRES Project. The DA's official confirmation of the establishment of the PMC with its final membership composition is being awaited. |
| 9. Nationwide Fishing Ports Development Package Project, Phase II | DOTC | 25th YLP |
P 1764 |
3-Aug-2000 | 15-Aug-2000 | DOTC to submit to the ICC a MOA among the DOTC , DA (BFAR/PFDA) and LGUs which would define the responsibilities of each party with regard to operation and maintenance of ports, revenue and cost sharing b/n NG and respective LGUs and land acquisition. | Per DOTC, draft MOAs among concerned agencies and LGUs have been drafted. |
| 10. 2nd Irrigation Systems Improvement Project (Change in Cost) | NIA | ADB |
P 1883.35 |
3-Aug-2000 | 15-Aug-2000 | NIA to submit to the ICC monthly reports on the ROW acquisition for the additional work. ROW should be settled prior to the start of implementation. | ROW acquisition schedule will be submitted by December 2000. NIA shall start submitting monthly reports on the status of ROW acquisition by Oct. 2000. |
| 11. Support to Agrarian Reform Communities in Central Mindanao | DAR | EU |
P 886.4 |
14-Jul-2000 | 15-Aug-2000 | DAR to: (1) include if possible the rural electrification component under the support infra component of the project; (2) implement the credit component subject to the NCC's favorable endorsement of detailed framework; (3) coordinate with other NGAs the provsion of infra, agri and livelihood development interventions. | ICC clearance will be issued upon approval by the ICC of the final design of the project's credit component. |
| 12. Communication and Navigation Surveillance/Air Traffic Management (CNS/ATN) | DOTC | 25TH YLP |
P 74,600 |
23-Oct-2000 | 28-Nov-2000 | ECC or CNC | Informed the DOTC of the required/pending documents on 31 October 2000. |
| 13. Cebu Light Rail Transit Project | DOTC | SYLP |
P 32,400 |
30-Oct-2000 | 28-Nov-2000 | Revised logframe and to conduct separate financial management study aimed at improving the financial viability of the project. | Informed the DOTC of the required/pending documents on 31 October 2000. |
| 14. Construction of Hydraulic Laboratory Structure | DPWH | GGAP |
P 354 |
23-Oct-2000 | 28-Nov-2000 | Submit 5-year research program for which the facility will be utilized, with clear indications of measurable targets. | Informed the DPWH of the required/pending documents on 31 October 2000. |
| 15. US$20 million Nordic Investment Bank Loan Facility | DBP | NIB |
$ 20.00 |
23-Oct-2000 | 28-Nov-2000 | List/Pipeline of prioritized projects for the facility (facility should be availed by firms with no/limited access to financial markets). | Informed the DBP I181 of the required/pending documents on 31 October 2000. |
| 16. Capability Building Program of the Bureau of Fire Protection | DILG-BFP | SYLP |
P 6,006 |
23-Oct-2000 | 28-Nov-2000 | (1) RDC from Cebu and Davao; (2) ECC; (3) Inclusion of the CY2001 Program Fund in the DILG budget ceiling; (4) endorsement of Davao City and Cities and, cities/municipalities of NCR to make the required lot donation./ MMDA endorsement of subject proposal. | Informed the DILG of the required/pending documents on 31 October 2000. Submitted RDC XI endorsement on 22 December 2000. |
| Category B | |||||||
| Category C | |||||||
| Legend:
Category A - projects whose ECCs are issued on a per component basis Category B - projects whose EIS shall be prepared during the detailed engineering/design phase Category C - BOT projects |