I. OVERVIEW
1. This Review is in compliance with NEDA Board instructions and
RA 8182, as amended by RA 8555, or “The ODA Act”,
which mandates NEDA to conduct annual reviews of the status of
implementation of all projects financed through Official Development
Assistance (ODA). A report must be submitted by NEDA to Congress
on the outcome of the ODA Portfolio Review by 30 June 2004.
2.
Pursuant to the ODA Act, the Government uses ODA to achieve equitable
growth and development through priority development projects for
the improvement of economic and social service facilities.
3.
In summary, the performance of the country’s ODA portfolio
continues to improve based on several indicators, and as recognized
by ODA partners. This improvement has been made possible by various
measures undertaken by government which are enumerated in this
report. Notably, the improvement in ODA performance occurred in
an environment of tight budget constraints and austerity measures.
Still, potential risks with respect to budget cover, procurement
and right - of - way acquisition have to be continuously monitored
and addressed. Similarly, the performance of LGUs, which have
an increasing share in the ODA portfolio, need to be closely monitored.
Areas for further improvement are recommended in this report.
4.
In the course of the Review, 28 agencies were met and consulted.
These are : Autonomous Region in Muslim Mindanao Social Fund for
Peace and Development PMO, Bases Conversion Development Authority
(BCDA), Department of Agriculture (DA), Department of Agrarian
Reform (DAR), Development Bank of the Philippines (DBP), Department
of Education (DepEd), Department of Environment and Natural Resources
(DENR), Department of Finance (DOF), Department of Health (DOH),
Department of Interior and Local Government (DILG), Department
of Public Works and Highways (DPWH), Department of Social Welfare
and Development (DSWD), Department of Tourism (DOT), Department
of Transportation and Communication (DOTC), Light Rail Transit
Authority (LRTA), Land Bank of the Philippines (LBP), Local Water
Utilities Administration (LWUA), Metropolitan Waterworks and Sewerage
System (MWSS), National Irrigation Administration (NIA), National
Power Corporation/National Transmission Corporation (NPC/TransCo),
Pasig River Rehabilitation Commission (PRRC), Philippine Economic
Zone Authority (PEZA) Philippine General Hospital (PGH), Philippine
Merchant Marine Academy (PMMA), Philippine National Oil Company
– Energy Development Corporation (PNOC – EDC), Philippine
Ports Authority (PPA), Subic Bay Metropolitan Authority (SBMA)
and Technical Education and Skills Development Authority (TESDA).
These agencies account for 95% of the ODA loans portfolio.
5. This report includes a section on procurement activities in
ODA projects, which will now be a regular feature of the annual
reviews. This section will (a) look into the time it takes for
the whole procurement process, from start of tender (or issuance
of bid documents) to the issuance of notice to proceed (NTP);
(b) review compliance of agencies with prescribed timelines in
RA 9184 or the Government Procurement Reform Act, (c) identify
causes of delays, and (d) recommend measures to be undertaken
to streamline the procurement process, or report measures already
put in place by agencies.
6.
As in the previous year, this report discusses, among others,
outputs and accomplishments of completed and ongoing ODA projects,
the ODA portfolio performance using various indicators, commitment
charges paid, and implementation issues encountered in 2003 and
measures to address them. In addition, lessons learned from past
reviews are compiled and reissued in this report.
7.
The report also aims to incorporate the reporting of project outcomes
and impacts as mandated in NEDA Board Resolution No. 3 s. 1999
and supported by NEDA Board Resolution No. 14 s. 1999 [(which
approves the Guidelines Incorporating Results Monitoring and Evaluation
(RME) in the Investment Coordination Committee (ICC) Approval
Process)]. 8.
This report is divided into two parts: Part I provides an overview
of the review process and the report’s scope and contents;
Part II describes the ODA loans portfolio, and discusses indicators
of portfolio performance, accomplishments and outputs of completed
projects, implementation issues, lessons learned and implications,
future budget requirements of ongoing projects, and prospects
for 2004.
II.
ODA LOANS PORTFOLIO
9.
This Review covers 189 active loans with a net commitment of US$10.9
billion, composed of 184 project loans supporting 156 projects,
and five (5) program loans. Project loans accounted for 93% or
US$10.1 billion, while program loans, 7% or US$0.8 billion (Annex
A-1). Over the last four years, ODA commitments have been decreasing
as a result of Government’s greater adherence to project
quality and fiscal discipline. From a peak of US$13.3 billion
in 2000, ODA loans commitment amounted to US$10.9 billion as of
31 December 2003, which is 8% lower than the 2002 figure and 18%
lower than the 2000 figure.
10.
Among funding sources, the Government of Japan through the Japan
Bank for International Cooperation (JBIC) remained as the largest
source of ODA loans, accounting for 62% (or US$6.8 billion with
79 loans) of the total ODA, followed by Asian Development Bank
(ADB) with 14% (or US$1.6 billion with 39 loans), and the World
Bank (WB) with 13% (or US$1.4 billion with 26 loans). Other Sources
(like Australia, Austria, China, DANIDA, European Investment Bank,
France, Germany, IFAD, Korea, Kuwait, NORDIC Development Fund,
OPEC, Spain and United Kingdom) accounted for the remaining US$1.1
billion from 45 loans, or 11% of the total ODA loans portfolio.
The amount of assistance from the Other Sources has increased
by US$493 million compared to the 2000 level of US$656 million
(from a share of 5% to 11%).
11.
Across development sectors, the bulk of ODA was channeled to Infrastructure
Development, which received 110 loans with an aggregate commitment
of US$6.9 billion or 69% of the total ODA loans portfolio. Second
was Agriculture, Agrarian Reform and Natural Resources, which
accounted for 17%, US$1.8 billion from 41 loans. Industry and
Services had 5%, US$498 million from 3 loans, while the Social
Reform and Development Sector had 9%, involving US$937 million
from 30 loans. In Infrastructure, Transportation obtained the
biggest share of US$4.9 billion (or 48%), followed by Water Resources,
US$930 million (or 9%) and the Energy, Power and Electrification,
US$781 million (or 8%) (Annex A-2). Since 2000, the social reform
and development sector’s share in the portfolio increased
from 6% to 9% compared to 2003 while there was a substantial decrease
in the share of the industry and services sector from 11% to 5%
in the same period.
12.
National Government (NG) agencies and local government units were
responsible for implementing 57% of the ODA project loans portfolio,
involving 114 loans with net commitment of US$5.8 billion. On
the other hand, government-owned and controlled corporations (GOCC)
and government financial institutions (GFI), administered 43%
(or US$4.3 billion) of the ODA project loans portfolio involving
64 loans (Annex A-3). There was a substantial increase in the
share of NG-implemented projects beginning 2000, from 48% to 57%
in 2003. Conversely, a decrease in the share of GOCCs/GFIs implemented
projects from 52% to 43% was noted over the same period.
13.
ODA loans may be further classified into (a) those that require
budget cover (e.g., those financing projects implemented by line
agencies and some GOCCs like NIA, those with MDFO as conduit),
and (b) those that do not (i.e., those financing projects of GOCCs/GFIs
and the program loans). The former accounts for 63% of the 2003
portfolio, which used to account for only 53% in 2000 (Annex A-
4). The 22 loans that pass through MDFO comprised 9% of the ODA
project loans portfolio in 2003 and 14% of the budget- dependent
portfolio for the same period (Annex A-5). Meanwhile, the 49 ODA
projects with LGU participation accounted for 18% of the projects
portfolio, a mere one percentage point increase over the share
recorded in 2000 (Annex A-6).
14.
The regional disaggregation in terms of project costs (loan proceeds
and GOP counterpart funds) of ODA-funded projects is shown in
Annex 7. About 29% is allotted to Luzon (excluding NCR), 15% to
NCR, 19% to Visayas and 16% to Mindanao.
15.
New Loans – New loans worth US$763 million, or 7% of the
total commitments, entered the portfolio in CY 2003. These include:
(a) six loans from JBIC (US$354 million); (b) three loans from
ADB (US$221 million); (c) three loans from WB (US$106 million);
and (d) one each from China, Spain, Germany and IFAD amounting
to a total commitment of US$82 million (Table 1).
16.
Loan Cancellations – Partial cancellations of US$422 million
were done in 29 loans as follows: (a) ADB, US$288 million; (b)
JBIC, US$73 million; (c) WB, US$29 million; and (d) Other funding
institutions, US$32 million (of which US$29 million is from EIB).
These cancellations were agreed upon with funding agencies to
clean up the portfolio of excess financing (e.g., due to foreign
exchange movement , reduction in scope of projects, or loan closing)
and dormant funds of slow-moving projects, and in the process
generate savings for the government on commitment fees in some
cases (Table 2).
A.
DEFINITION OF INDICATORS
17.
Four indicators of ODA absorptive capacity are presented. These
are: (1) disbursement level; (2) disbursement rate; (3) availment
rate; and (4) disbursement ratio. These data on loan utilization
can be used as proxy indicators of the physical performance of
the different programs and projects.
18.
The disbursement level is the actual amount of disbursements (in
dollar terms) from all ODA loans for the period January to December
2003.
19.
The disbursement rate is defined as actual disbursements as a
percentage of target disbursements for a given period. Targets
are set on an annual and quarterly basis, in consultation between
implementing agencies and funding institutions (ADB, JBIC and
WB only). This indicator reflects both on the planning and implementation
capacities of agencies. Very high and very low rates can reflect
poor planning (too optimistic targets or under-targeting) or poor
implementation. Annual targets should be consistent with finishing
a project within its implementation schedule and the loan period.
20.
The availment rate, which has been reported by the NEDA in all
past portfolio reviews, is defined as the cumulative actual disbursements
as a percentage of cumulative scheduled disbursements (references:
loan agreement, credit agreement, appraisal report, supply contracts,
or generated S-curves) reckoned from the start of implementation
of all projects up to December 2003. This captures the historical
performance of a project from start to completion. Backlogs incurred
at the start of the implementation, if not fully recovered, can
pull down the availment rate for the remainder of the project
life. It is imperative that implementing agencies are able to
carefully review the disbursement targets based on aforementioned
references. For ADB, WB and other financing sources that charge
commitment fees, the disbursement targets set at loan signing
give an indication of the commitment fees that may have to be
paid over the life of a project.
21.
Finally, the disbursement ratio is the ratio of actual disbursements
in 2003 to the net loan amount available at the beginning of 2003
plus the amount of new loans that became effective less loan cancellations
during the year. It is the indicator commonly prescribed by the
funding institutions.
22.
The ideal availment and disbursement rates are 100%. On the other
hand, a disbursement ratio in the range of 18-20% is considered
normal, based on assumptions of five-year implementation period
and straight-line schedule of disbursements for a considerably
large and uniformly distributed (in terms of age) pool of projects.
However, disbursement ratios depend on the stage of project implementation;
a 5% disbursement ratio for a project at detailed engineering
stage could be acceptable.
B.
PORTFOLIO PERFORMANCE
23.
Disbursement Level. The total ODA disbursements of the country
in 2003 reached US$1.4 billion, compared to US$1.0 billion in
2002, or an increase of US$370 million or 36% (Annex B-1). Project
loans alone registered a 14% increase, from US$935 million to
US$1,068 million, while program loans posted a 238% increase,
from US$100 million to US$338 million. Assuming loan disbursement
is a proxy indicator of physical accomplishments, the value of
projects from ODA loans increased significantly.
24.
In the case of program loans, GOP was able to substantially comply
with major loan conditionalities under the Metro Manila Air Quality
Improvement Program (JBIC and ADB) and the Pasig River Environmental
Management and Rehabilitation Sector Program (ADB) resulting in
the release of the final tranche from these loans. Except for
the Second Non-Bank Financial Governance Program II (ADB), all
ongoing program loans are now fully availed.
25.
Agencies where a significant drop in disbursement levels were
noted are: DILG, DOTC, NIA and NPC (Annex B-2). Reasons cited
by the implementing agencies for the decrease in disbursement
levels were: unavailability of counterpart funds changes in priorities
of LGUs; completion of project or loan closure; procurement delays;
insufficient budget cover and inability of LGUs to provide equity.
26.
All sectors and sub-sectors posted increases in disbursement levels
except for the Energy, Power and Electrification sub-sector which
recorded a decrease of 30 percent (from US$97 million to US$68
million). The reduction is due to the substantial reduction of
disbursements in the NPC/TransCo portfolio as a result of the
winding-down of the major power projects such as the Transmission
Grid Reinforcement Project, Luzon Grid Transmission Projects Associated
with Private Power Projects and Power Transmission Reinforcement
Project in 2003, as there had been no new investments by government
in the sector consistent with the Electric Power Industry Reform
Act of 2001 that encourages private inflow of capital to the sector
(Annex B-3).
27.
Projects supported by the GAA (budget-dependent) and those which
are non-budget dependent posted increases in disbursement levels
in 2003 over the 2002 level with 5% and 29%. However, the share
of budget-dependent projects in the 2003 total disbursements decreased
by 5 percentage points from 61% to 56% (Annex B-4).
28.
Projects involving LGUs where MDFO serves as conduit registered
a 22% increase in disbursement levels from US$87 million to US$106
million (Annex B-5).
29.
Disbursement Rate. On average, implementing agencies achieved
only 86% of the targeted disbursements of projects supported by
ODA. Across agencies and sectors, disbursement rates vary widely
indicating the need to review the target-setting process of many
agencies (Annexes C-1 and C2).
30. On a quarterly basis, disbursement rates fluctuate from one
quarter to another, for example, from 129% to 70% to 74% to 84%
from the first to the fourth quarters. First quarter performance
has been noted to be driven by JBIC-assisted projects, as the
first quarter coincides with the closing quarter of the JBIC fiscal
year. (Annex C-3). Non-budget dependent projects continue to improve
its disbursement rate from 69% in 2001 to 77% in 2002 to 98% in
2003 while budget-dependent projects disbursement rates were almost
constant at 79% - 80% levels for the same period (Annex C-4).
31.
Availment Rate. Availment rate in 2003 was 61%, two percentage
points higher than the 59% recorded in 2002 ( Annex D-1 ). However,
it may be noted that only the JBIC portfolio is below the 2003
average availment rate. It may be noted that cancellations are
rare in the JBIC portfolio because there are no commitment fees.
Since availment rate is a function of targets in foreign currencies
which are determined as early as the time of the signing of the
loaning agreement, the peso equivalent of these targets have increased,
sometimes implying a corresponding increase in physical targets,
and additional budget requirement unless the funds are cancelled.
Backlogs in project startup, unless addressed fully early on,
will adversely affect availment rates until the loan closing date.
32.
The social reform and development sector registered an availment
rate of 68%, highest among the different sectors (Annex D-2).
An upward trend has been noted in availment rates of this sector
from 49% in 2001, 59% in 2002 and 68% in 2003. On the other hand,
the infrastructure sector had a rate of 56%, which is five percentage
points below the average. It may be noted that budget constraint,
procurement and ROW issues are prevalent in this sector.
33.
Disbursement Ratio. The average disbursement ratio for the three
biggest portfolios was 19%, six percentage point higher than the
13% recorded in 2002 (Annex E-1). ADB recorded a 33.7% disbursement
ratio, WB 21.6%, while JBIC registered 15.7%. Again, it may be
noted that partial loan cancellation is rare in the JBIC portfolio
because no commitment fees are charged for undisbursed amounts.
It may be recalled that funding institutions called on GOP to
raise its disbursement ratio to 20% by 2004 during the 2002 Consultative
Group Meeting.
34.
Loan Extensions. Sixty- six loans worth US$3.4 billion or 31 percent
of the ODA portfolio, including 20 loans (worth US$1.2 billion)
which closed in 2003, were on extended periods of 2.0 years average
beyond their original loan closing dates (Table 3). This is lower
than the 68 loans reported in 2002. Of the 46 ongoing loans which
have exceeded original duration, 24 loans require extensions of
more than a year, while 22 loans require less than one year.
35.
Additional Budget Requirements. Twenty-nine projects will require
additional budget from 2004 onwards (Table 4) with an aggregate
amount of about P24 billion. During the year, eleven projects
were re-evaluated by the ICC in 2003 for increases in the original
ICC-approved project cost.
36.
In general, the following are the justifications given by IAs
for the additional budget requirements: (a) foreign exchange rate
movement; (b) change in scope/additional works; and (c) increase
in right-of-way (ROW) acquisition cost.
37.
Commitment Fees. For the ongoing projects, cumulative commitment
fees paid by the government to ADB, WB and other funding institutions
as of December 2003, amounted to US$45 million. In 2003 alone,
US$9.5 million was paid in commitment fees. Among national government
agencies, commitment fees paid by GOP for DPWH and DOTC projects
were US$0.97 million and US$1.2 million, respectively. Among GFIs,
DBP and LBP paid commitment fees of US$0.2 million and US$0.5
million, respectively (Annex F-1).
C.
ACCOMPLISHMENTS AND OUTPUTS OF PROJECTS
38. Twenty loans amounting to US$1.2 billion were reported as
closed/fully availed during the year (Table 5) consisting of:
five loans from ADB (US$353 million); seven loans from JBIC (US$793
million); two from WB (US$ 21 million); and one each from Germany,
IFAD, Korea, France, DANIDA and Spain (a total of US$674 milllion).
Completed
Projects (Table 6)
Infrastructure
39. Two projects under DPWH were
completed in 2003. Under the Philippine-Japan Friendship Highway
Rehabilitation Project I, accomplishments include: 250 km of roads
were rehabilitated; one bridge was repaired and one bridge was
constructed. Meanwhile, under the Philippine-Japan Friendship
Highway Rehabilitation Project II, 379 km of roads were rehabilitated,
64 km of portland cement concrete pavement /asphalt concrete (PCCP/AC)
overlay were constructed/rehabilitated, five different types of
bridges repaired and one bridge constructed.
40. Under the Mindanao Power Transmission
Project, construction of 18.0 circuit-kilometers (cKt-kms) in
Montevista-Monkayo 69 kilovolts (kV) transmission lines (T/L),
29.0 cKt-kms in Nuling-Midsayap 69 kV T/L, 15.0 cKt-kms in Tagum-Assuncion
69 kV T/L were completed. Also, 21 wooden poles were erected in
Maasim-Kiamba 69 kV T/L. These completed structures reinforce
the existing 69 kV transmission line and transformer capacity
in the Mindanao regions to accommodate and serve the growing power
demand in the area.
41. The Spain-assisted Maritime
Safety Improvement Project III was able to complete the construction
of 87 lighthouses; installed 120 imported lighthouse equipment
and trained 94 PCG personnel on the operation and maintenance
of lighthouses.
Agriculture, Agrarian Reform and
Natural Resources
42. Under the DENR’s Forestry
Sector Project, 57,652 hectares of watershed areas and 11,491
hectares of mangrove areas or a total of 69,143 hectares were
established by private organizations (Pos) nationwide. The tenured
(POs) in 24 watersheds and 12 mangrove subprojects are now protecting
and maintaining the established forests and are undertaking economic
activities to raise incomes and sustain project gains/initiative.
Forty-seven POs were organized and strengthened in the watershed
subprojects and 23 POs in the mangrove subprojects, while 64 Community
Based Forestry Management Agreements (CBFMAs) were granted to
59 POs implementing watershed and mangrove subprojects. The Project
was also able to rehabilitate more than 110 kms of road, established
25 water systems and constructed 20 bridges, 19.4 kms pathway
and 13 causeway/wharfs. In addition, 274 livelihood projects were
implemented.
43. Under DENR’s Metro Manila Air Quality Improvement Sector
Development Program of DENR, a total of 3,173 firms were identified
as major sources of air pollution within Region 3, 4A and NCR
while 703 notices of violation were issued to non-complying industries.
Five private laboratories were accredited to undertake analysis
of air emission standards. In addition, six computerized Permit
Administration System (CPAS) were installed and maintained, 20
trainings were conducted on industrial emission monitoring and
inventory. The attainment of the objectives of the Project is
now being monitored, i.e., air pollution from mobile and stationary
sources will be substantially mitigated, fuel quality will be
improved; emissions from vehicular use reduced; traffic congestion
reduced through improved traffic flow; and ambient air quality
monitoring strengthened.
44. Some 1,636-farm families benefited
with the provision of irrigation water in 6,762 hectares of new
areas under the Malitubog-Maridagao Irrigation Project implemented
by NIA. With the completion of the Project, rice production is
expected to increase through intensive irrigation and drainage
systems.
Social Reform and Development
45. Under the SZOPAD Social Fund
Project, completed facilities include : 219 Madrasah classrooms,
131 school classrooms, 1,198 meters of pedestrian bridges, 45
Barangay Health Stations, eight (8) timber ports, and one (1)
training center. Also completed were the renovation of five (5)
Madrasah classrooms, 41 school classrooms, one (1) Barangay Health
Station, two (2) small irrigation systems and three (3) dug wells.
46. The WB-assisted Women’s
Health and Safe Motherhood Project produced the following outputs;
(a) upgraded obstetric units in 70 Rural Health Units (RHUs) and
74 Barangay Health Stations (BHSs) in 36 provinces, including
the provision of furniture and equipment (b) trained 2,450 Public
Health Providers, 26 Project Coordinators, 16 Trainors on the
Syndromic Approach to Diagnosis and Management of Reproductive
Tract Infection/ Sexually Transmitted Disease (RTI/STD) care in
10 provinces in Visayas and Mindanao and public health workers
in the 70 RHUs and 74 BHSs in 36 provinces; and (c) constructed
and provided 10 RTI/STD clinics with diagnostic equipment in the
36 provinces.
Industry
and Services
47. Under the Rural Micro-Enterprise Finance Project (ADB and
IFAD), 1,124,605 subprojects worth P2.5 billion were extended
by People’s Credit and Finance Corporation (PCFC) to 300,000
self-help groups. These subprojects have helped increase family
income by 50% and most of the families covered are now above the
poverty line. Meanwhile, under the Metro Manila Quality Improvement
Project – Air Pollution Control Credit facility, four environment
subprojects namely: Vallacar Transit and Rural Transit Mindanao,
both in Region VI, Angeles Power Incorporated in Region III, and
Roxas Holdings Inc. in Region IV were financed amounting to some
P298 million.
Ongoing
Projects
48.
Under the infrastructure development sector, 11 bridges were constructed
and 54 bridges were repaired/retrofitted. Further, 251 kilometers
of asphalt concrete overlay and 164 kilometers of portland concrete
cement pavement were completed. In Metro Manila, construction
of EDSA/Quezon Avenue Interchange and C-5/Ortigas Avenue Extension
Interchange were completed.
49.
Moreover, three transmission lines projects were energized as
follows: a) Power Transmission Reinforcement Project; b) Luzon
Grid Transmission Project Associated with Private Power Project
(Ilijan Project); and c) Luzon Grid Transmission Project Associated
with Private Power Project (Casecnan Hydro Project). Air navigation
facilities in Davao, Palawan, Tagbilaran, NAIA, Tuguegarao, Naga,
Mt. Majic, Jomalig, Cauayan, Caticlan, Zamboanga, Baguio, Tagaytay,
Laoag and Kalibo airports were upgraded and modernized under the
Nationwide Air Navigation Facility Modernization Project III while
15 lighthouses were completed under the Maritime Safety and Improvement
Project III.
50.
In addition, a total of 4,182 rural water facilities were installed
in Regions II, IV-A, IV-B, V, VI, VIII, IX, XIII, ARMM and CAR,
consisting of 1,431 shallow wells, 1,081(new) and 686 (rehabilitated)
deep wells, 828 spring development and 147 spring rehabilitation
project. A total of 415 housing units at the Initial Resettlement
Area and Banza Pedestrian Bridge were constructed under the Lower
Agusan Development Project. Under the Agno and Allied Rivers Urgent
Rehabilitation Project, completed were the construction of the
Bugallon Shortcut Channel and Bridge, Domalandan Bridge River
Training Works, revetment works in Upper Sinocalan, Tarlac and
Lower Agno and Tarlac River Interim Improvement Works.
51.
NIA provided irrigation to 37,083 hectares of new areas and rehabilitated
120,515 hectares in existing irrigation systems through its ODA-assisted
projects.
52.
Under the health sector, health facilities in five district hospitals
were upgraded/renovated while health facilities in one district,
three rural health units and seven barangay health stations were
replaced/constructed under the Integrated Community Health Service
Project. In addition, various equipment for two provincial hospitals
and 15 district hospitals were procured and delivered.
53.
In the education sector, 1,523 classrooms were constructed/rehabilitated,
475,872 sets/units of tables and chairs were delivered to schools
nationwide while 25,882 schools were provided with funds for the
repair and maintenance of school buildings under the Social Expenditures
Management Project I. In the Secondary Education Development and
Improvement Project, 3.2 million textbooks and 54,526 teacher’s
manuals were delivered and supplied.
54.
Under the Third Elementary Education Project, trainings were given
to 108,066 teachers, 731 district supervisors. A total of 12,837
school managers attended various division-based trainings while
72,088 trainees attended various trainings on support component.
Moreover, more than 15 million instructional materials and textbooks
were delivered.
D.
KEY IMPLEMENTATION ISSUES (Table 7)
55. Budget. The budget is a critical
issue in ODA implementation. It has several facets: First, appropriation
or budget cover is required not just for GOP counterpart, but
also for loan proceeds of ODA projects of NG agencies. Without
a line item or with insufficient allocation in GAA, an ODA project
will have to depend on agency realignments or compete for the
FAPs Support Fund (proposed to be abolished in 2004). Second,
DBM action is required for administrative issuances like Notice
of Cash Allocation (NCA) for counterpart funds and special accounts,
and Non-Cash Availment Authority (NCAA) for direct payment through
loan proceeds. Lack of revenues or fiscal discipline measures
could influence DBM action. Third, having received adequate authority
or cash allocation from DBM, agencies still have to determine
priority to any given ODA project, as against other projects or
other needs.
56. For budget-dependent ODA projects,
the 2003 adjusted program was P39.5 billion (inclusive of loan
proceeds and counterpart funds) of which 69% was for capital outlays
and 31% for current operating expenditures. This amount is seven
percent less than the 2002 program of P42.2 billion consisting
of 59% capital outlay and 41% current operating expenditures.
Capital outlay for ODA projects in 2003, amounting to P27 billion,
accounted for 26% of the P105 billion total NG capital outlays.
The total NG budget in 2003 was P811.5 billion.
57. In 2003, several projects
were reported to have encountered severe budget cover problems.
These projects are mostly those using MDFO as conduit (22 projects),
flood control projects of DPWH, projects of DILG and DOTC, among
others. In particular, these projects either have unprogrammed
budgets in the GAA or have physical accomplishments whose financial
requirements exceeded the available budget cover for the year.
58. In the case of DPWH, only
P18.8 billion was appropriated in 2003 compared to P19.9 billion
in 2002 (a reduction of 6%). DPWH reported that the Congressional
initiatives in the DPWH budget increased from P14.8 billion in
2002 to P15.5 billion in 2003.
59. Some agencies were observed
by DBM to have allowed direct payments from funding sources to
contractors and suppliers, in excess of their budget cover. While
this enabled ODA absorption, this adversely affects NG fiscal
programming. DBM is now more strictly monitoring direct payments.
60. On the timing of the release
of the available allocations, several implementing agencies (e.g.,
DPWH, DA, DAR, TESDA and DENR) reported that the bulk was released
in the latter half of 2003. This reportedly caused low utilization
of said funds as these can not all be disbursed by yearend and
late/non-payment of progress billings for works accomplished,
services rendered or goods procured.
61. The 2003 GAA (RA 9206) was
passed only in April 2003. Thus for January to April, agencies
were operating on 2002 budget. It may be noted that in four fiscal
years from 2001 to 2004, the government had a reenacted budget
twice, and a late budget once, which created confusion and uncertainty
in ODA implementation.
64. A special provision in the
2003 GAA prohibited DPWH from awarding contracts above approved
budget for the contract (or ABC). DPWH reported that about P7.6
billion worth of contracts were affected. The Department of Justice
issued an opinion in October 2003 that projects or contracts governed
by any treaty or agreement or international executive agreement
existing as of the effective date of the CY2003 GAA are excluded
from the said prohibition. Further, the DOJ noted that under the
Foreign Borrowings Law (R.A. 4860 as amended), the President is
empowered to waive the application of any law imposing restrictions
on the procurement of goods and services.
65. Arising from the budget constraint
is the VAT issue and delayed payments to contractors raised by
Government of Japan. While DBM has allowed payment of VAT, these
should be sourced within the agency’s regular budget, thus
competing with allocations for the implementation of ongoing foreign
–assisted projects.
66. Procurement. Procurement is
a perennial issue, always raised by lending institutions, and
thus poses one of the biggest challenges to facilitating project
implementation. Two periods have to be closely observed in procurement:
(a) the total time to complete the procurement process, including
processing times of GOP and lending institutions, which basically
shows how long before civil works implementation, etc. can start,
and (b) an agency’s compliance with the prescribed timelines
in RA 9184, for evaluation of bids, contract award, and issuance
of notice to proceed (NTP) by GOP agencies, which should exclude
the processing times of lending institutions.
67. Of the 49 civil works, 29
consulting services and 60 goods contract packages reviewed (cutoff:
NTPs issued in 2003), it may be noted that procurement could take
as long as 19 months for consulting services, 35 months for civil
works and 18 months for supply of goods (from submission of bids
to issuance of notice to proceed). On the average, however, award
of consultancy services took 9.26 months, civil works, 9.53 months
and supply of goods, 7.9 months for said contracts.
68. Netting-out the processing
time by funding institutions, the actual periods from submission
of bids to issuance of NTPs on the average are as follows: about
6.85 months for consulting services, 6.43 months for civil works
and 6.57 months for supply of goods. These are beyond the prescribed
periods under RA 9184 or the Government Procurement Reform Act
of 4.4 months for national government agency procurement and 4.7
months for government corporation procurement (Table 8).
69. For civil works contracts,
delays were observed in various stages. From start of tender to
submission of bids, major factors are: differences between GOP
and the funding institutions on the pre-qualification criteria
and the results of pre-qualification. From submission of bids
to completion of evaluation, major factor is unclear evaluation
parameters and criteria particularly in its interpretation. From
completion of evaluation of bids to the award of contract and
issuance of NTPs, major factors are: filing of complaints or court
cases by the losing bidders, non-concurrence of funding institutions,
too many signatories or clearing authorities required, and changes
in management in the implementing agencies. The special provision
in the 2003 GAA prohibiting DPWH to award contracts above approved
budget for the contract (ABC ) affected bulk of civil works contracts
of DPWH.
70. In general, the procurement
process becomes protracted for the following reasons: failure
of bidding when bids are non-responsive, complaints of losing
bidders, impasse in negotiations, conflict in procurement guidelines
of GOP and the financing source, court-related issues, and non-concurrence
of funding institution at different stages of the bidding, and
changes in leadership in a number of implementing agencies (e.g.,
in DPWH, DepEd, DENR, DOTC and TESDA) which affected procurement
when new management exercised due diligence and required reviews
of previous decisions.
71. Right-of-way acquisition and
resettlement. Right-of-way acquisition (ROWA) can be delayed because
of budget non-availability, the lengthy processes of acquisition
and relocation - including negotiations, legal procedures and
documentation requirements despite RA 9874, and in certain cases,
public opposition. By themselves, ROWA and resettlement are inherently
challenging and time-consuming activities. When compounded by
other issues such as differences in guidelines of funding institutions
and the government, these activities can be a serious bottleneck.
72. A number of projects continue
to be affected by delays in ROWA such as the Sixth Road Project,
MM Flood Control West of Mangahan Project, KAMANAVA Area Flood
Control Project, Lower Agusan Development Project Stage I, Phase
II, among others.
73. Relending. Relending projects
of DBP and LBP, which comprise about 12% of the portfolio, showed
signs of recovery as disbursement levels in 2003 increased by
more than 200 percent compared to 2002.
74. The current economic environment
has allowed credit expansion in the domestic industry, facilitating
the approval of P6.2 billion (DBP) and P2.7 billion (LBP) in sub-loans
to its clients in 2003. Projects that are on track are LBP’s
Third Rural Finance, Water District Development and LGU Support
Credit projects, and DBP’s Industrial Support Services Project.
Meanwhile, LBP’s Metro Manila Air Quality Improvement, LGU
Private Infra Project Development Facility and Mindanao Basic
Urban Services projects and DBP’s Domestic Shipping Modernization
Project II, LGU Urban Water and Sanitation Project (APL2) and
Fund for Technical Education and Skills Development Project need
to be monitored closely.
75. LGU participation. ODA projects
with direct LGU participation accounted for 18 percent of the
portfolio. LGU performance was affected by several factors, such
as, availability of LGU counterpart funds, LGU counterpart staff
and their capacity for project preparation and implementation,
non-compliance by LGU with their commitments, and changes in LGU
priorities. In some instances, LGUs withdrew from ODA projects
after GOP provided grants on project preparation and implemented
the projects using regular relending programs (not ODA-financed)
of GFIs.
76. There are divergent opinions
on LGU capability-building components of ODA projects. One opinion
is that NG through several agencies has provided more than enough
assistance for LGU training over the years. Another is that some
LGUs that are current beneficiaries of ODA are not getting necessary
assistance for capability building. A coherent strategy for LGU
capability-building needs to formulated, that will avoid duplication
of courses, sharpen targeting of LGUs, and is demand-driven.
77. Roles of Agencies. The roles
of several NG agencies in ODA project implementation need to be
reviewed vis-à-vis their major final outputs (MFOs) and
the MFOs of other agencies. DILG implements a wide range of projects
catering to LGUs like bridges, power, water supply, social welfare
and social infrastructure. This raises questions on the capability
and expertise of DILG to deliver a wide array of services. Among
the alternative roles for DILG that should be studied are: (a)
lead agency for selected ODA projects catering to LGUs, (b) oversight
agency for LGUs in ODA projects to be implemented by different
other agencies, or (c) lead agency for governance-related projects
only.
78. DSWD is implementing sub-projects,
like water systems (levels 1 and 2), farm-to-market roads, irrigation
and post harvest facilities, aside from multi-purpose buildings,
day care centers, and school buildings, under KALAHI that are
similar to sub-projects implemented by DA, DAR, DepEd, etc. On
the other hand, DAR is implementing a rural electrification project
for ARCs.
79. DOF, an oversight agency,
is lead agency for Community Base Resource Management Project
(CBRMP) and Local Government Finance Infrastructure Development
Project (LOGOFIND).
80. Changes in Scope and Increases
in Costs. Changes in project scope and increases in project cost
normally should be minimal or avoided when project preparation
is adequate, although some unforeseeable circumstances could warrant
them. In many cases, however, such changes in scope and cost appear
to arise due to poor or lack of project preparation. During the
year, a total of 25 projects were re-evaluated and approved by
ICC because of changes in scope and cost (Table 9).
81. Other issues. Other issues
that affected ODA performance in varying degrees were delayed
issuance of environmental compliance certificate, poor performance
of contractors and unstable peace and order situation.
82. Changes in heads of agencies
(DPWH, DENR , DOTC , TESDA) and LGUs have been observed to have
significant impact on implementation of ODA projects, either negative
or positive. In many cases, the result is delays in award of contracts,
because of repeat reviews of contracts for due diligence, or in
certain cases, even changes in project design. In a few cases,
the result is positive, such as when the new management became
more proactive in addressing implementation bottlenecks.
E.
MEASURES TAKEN IN 2003
83.
In general, the measures that were recommended in last year’s
review were pursued by the concerned implementing and oversight
agencies. As a result, the following were noted: (a) Attention
was focused on ADB portfolio and the subsequent restructuring
of portfolio led to the cancellation of the Grains Sector Program
Loan (US$70 million) and the partial cancellation of the Metro
Manila Air Quality Improvement Project (US$21.3 million). This
led to improvement in the ADB portfolio’s performance and
indicators, i.e., disbursement rate increased by 10 percentage
points to 89%, disbursement ratio by 16.8 percentage points to
33.7%, availment rate by 5.6 percentage points to 72.1%; and (b)
GOCCs/GFIs disbursement level increased by almost 20 percent.
86.
In line with the government’s target to maintain a budget
deficit of P202 billion in 2003, the DBCC and ICC jointly conducted
an ODA portfolio review in early 2003 with the following objectives:
to review the implementation progress of major ODA-funded projects,
recommend deficit-neutral measures to improve ODA performance,
and ensure sufficient budget support for 2003 onwards for high
priority projects. The proposed dispositive actions were: cancellation
of excess financing for 6 projects amounting to US$31 million,
rephasing of implementation schedules for 15 projects, reduction
in scope for 10 projects; and tapping of other sources of financing
(LGUs or GOCCs) for 4 projects. To date, US$7.2 million of excess
financing was already cancelled, implementation periods of 6 projects
were rescheduled; scope of 6 projects were reduced, and other
sources of financing for 2 projects were identified and approved.
87.
To improve public expenditure management and fiscal programming,
a new ICC policy was adopted in November 2003 requiring resolution
of budgetary issues prior to ICC deliberation of new project proposals
or requests related to ongoing projects. However, even before
this, the ICC had been requiring submissions by agencies of its
medium-term investment programs and DBM-certified budget strategies.
88.
Project Implementation Officers (PIO) continued to keep close
supervision over ODA project implementation. PIOs are senior officials
(of Undersecretary or Assistant Secretary rank) designated in
all agencies implementing ODA-funded projects. Their main responsibilities
are to lead the agencies in implementing catch–up programs
for delayed and slow-moving projects, to closely monitor progress
of implementation and to coordinate with concerned agencies to
resolve bottlenecks. The PIOs together with oversight agencies
met quarterly in 2003 to address issues affecting project implementation,
share good practices, and be apprised of recent policies and procedures
on ODA.
89.
The Executive Order on conversion of MDFO to MFC was issued December
2003. MDFO continued to assist implementing agencies in the training
of LGU personnel to handle financial transactions and prepare
documentation requirements. Moreover, capability - building measures
for LGUs on procurement and project implementation continued.
It was observed, however, that the numerous training initiatives
have taken away time from LGUs in implementing project activities.
90.
Beginning January 2003, the revised NG-LGU cost sharing policy
will apply to new projects. This policy was issued to rationalize
terms of financial assistance to LGUs and channel financial assistance
to credit-worthy LGUs. It also partially corrects the distortion
of Internal Revenue Allotment (IRA) formula which favors more
the cities than municipalities and provinces, and expands coverage
to include other devolved activities with greater impact on development.
91.
Executive Order 109-A was issued on 18 September 2003, amending
EO 109, to conform with the provisions of the new Procurement
Law. This EO also delegates authority to heads of agencies and
their designated officials for the approval of selected contracts.
NEDA’s approval of contracts will be required only until
such time Government Procurement Policy Board or GPPB exercises
its authority to approve contracts. Executive Order No. 109, which
was issued on 27 May 2002, streamlined the rules and procedures
on the review and approval of contracts, and granted agencies
full responsibility for implementation of competitively tendered
contracts.
92.
In 2003, DPWH continued to strictly enforce Department Order No.
50 dated 6 February 2002 on the Approval of Design Plans Prepared
by DPWH Consultants. This Order requires that the design plans
state that the design consultants be held fully responsible for
the failure of the facility due to faulty design except for changes
made without the conformity of the consultant. The design consultant
shall also be liable for additional costs for major changes due
to faulty or defective design.
93.
DBM issued a circular on 13 March 2003 to rationalize the establishment,
restructuring and operation of project management offices or PMOs.
With this circular, PMOs will be integrated into the regular agency
structure to optimize use of physical and financial resources
and strengthen overall project performance monitoring. This will
also ensure faster mobilization for new projects, as new PMOs
need not be created every time there is a new project.
94.
In the preparation of the 2003 (and 2004) agency budgets, DBM
instructed that regular agency funds serve as counterpart for
foreign-assisted projects, to make full use of agency budgets
and ensure resource optimization in the government. Grant-assisted
projects were most affected by this arrangement, since before,
counterpart funds for such projects were automatically allotted
above the agency budget ceiling.
95.
The ICC approved restructuring in the following projects: a) extensions
by more than a year of the loan period of 16 loans; b) extensions
by a year or less of the loan period of 12 loans; c) increase
in scope of 16 projects; and d) increase in project cost of 12
projects (Table 9).
96.
The ICC instructed its Secretariat to generate rules of thumb
for preparing ROW and resettlement cost estimates to improve the
preparation of cost estimates and project appraisal in general
in future projects. The ICC Secretariat has solicited data from
key infrastructure agencies for a comparative study on original
cost estimates versus the actual cost of ROW and acquisition and
resettlement.
97.
Technical - level joint portfolio reviews continued to be conducted
quarterly with the three biggest funding agencies (ADB, JBIC and
WB) to identify specific issues affecting ODA performance. Inter-agency
follow-up and problem-solving sessions were conducted subsequently
to address major obstacles. During the Consultative Group meeting
with the donor community, the government offered concrete recommendations
to improve ODA performance.
F. LESSONS
LEARNED AND IMPLICATIONS
98. Project Administration – The project manager is the
key player in project implementation. On many occasions, it has
been noted that the success of project implementation can be equated
with the capability of the project manager. It is therefore very
important that the designation of project managers be a highly
competitive and objective process with a view to selecting the
most qualified person for the job. If disruptions in project implementation
are to be minimized, the process should be shielded from changes
in administration. A pool of competent project managers may be
developed within implementing agencies, especially those with
a steady pipeline of projects.
99.
Continuous capability building and training for project managers
as well as other key project personnel should be supported. In
particular, familiarization courses with procurement guidelines
of funding institutions should be regularly conducted. This should
be true especially for units that are implementing projects for
the first time.
100.
Sometimes, delays in procurement processes could be traced to
indecisiveness arising from lack of familiarity with procurement
guidelines. Knowledge and experience specifically on dealing with
the differences between GOP and funding agency guidelines should
be disseminated among project managers across all agencies.
101.
The project manager should work in tandem with the project financial
specialist. Physical targets should be linked with disbursement
projections to ensure that implementation programs are realistic
and will be supported with available funds.
102.
The circular of the Department of Budget and Management on Project
Management Offices (PMOs) needs to be finalized and disseminated
in order that implementing agencies with pending requests for
additional project personnel can take appropriate actions immediately.
The draft circular specifies the guidelines in rationalizing PMOs
for both locally-funded and foreign-assisted projects. It is based
on the principle of “scrap and build” and also specifies
the conditions on when a PMO may be established.
103.
For new projects, it is vital to set up a unit devoted to the
implementation of a project before a loan becomes effective. Moreover,
the personnel of the unit must be properly apprised about pertinent
GOP and funding agency rules and procedures.
104.
Funds Flow from Special Accounts – Flow of funds from special
accounts should be closely tracked by the PMO especially after
a request for withdrawal has been submitted to the funding institution.
Close coordination with the funding agency should also be made
to ensure that documents submitted are correct. If bottlenecks
are observed, PMO must be proactive in resolving them.
105.
Utmost efficiency in use of special accounts by implementing agencies
should be practiced. Note that replenishment of special accounts
is already considered as a loan disbursement, for which GOP will
be charged interest whether the implementing agency uses the funds
or not. In view of this, ways of charging financial costs of actions
of implementing agencies in project implementation, such as replenishment
of special accounts, to their respective agency budget ceilings
must be instituted.
106.
A few agencies failed to fully liquidate special accounts of completed
projects reportedly due to foreign exchange losses. Based on this
experience, it may be prudent to maintain special accounts in
original loan currency.
107.
Projects Involving Local Entities (LGUs and Water Districts) –
Projects involving the participation of local entities usually
require longer time for preparation, specifically before a memorandum
of agreement between the implementing agency and the local entities
is put in place. This should be factored into the implementation
design and schedule of a project. The more LGUs and water districts
are involved, the longer should be the time allowed.
108.
The impact of changes in administration at the local level, especially
after elections, on project implementation should be anticipated.
Possible disruptions may include changes in project personnel,
changes in priorities, and withdrawal of funding support. Scheduling
of important project milestones should be done with this considered.
109.
Ways to charge the financial cost (e.g., commitment fees, sunk
consultancy costs, etc.) of delays attributable to or withdrawals
of local entities to the local entities themselves should be actively
pursued. At the time of project appraisal, even before sub-project
agreements are finalized, commitments from LGUs/WDs to push through
with projects should be backed by Internal Revenue Allotment (IRA)
intercept or equivalent provisions.
110.
At the same time, a performance reporting system on local entities
should be considered by Municipal Development Fund Office (MDFO),
Local Water Utilities Administration (LWUA) and DILG that would
make NG agencies aware of their performance in other projects
with other NG agencies. Other NG agencies should be made aware
of the track record of LGUs/WDs in implementing ODA projects.
111.
Duplication of NG efforts in providing technical assistance and
capability-building programs to LGUs should be avoided. One way
to reduce, if not prevent this, is for NG not to provide full
grants to LGUs but to require LGUs to put up appropriate counterpart
costs. Likewise, the cooperation of DILG in this regard may be
sought.
112.
Continuous and closer coordination with MDFO should be sustained
by implementing agencies toward streamlining procedures and requirements,
and facilitating faster implementation of projects according to
their respective project design and requirements.
113.
Commitment Fees – Different funding institutions have different
methods of computing commitment fees. This information is available
even at the time of project appraisal, and may be taken into consideration
when a project is being presented for approval.
114.
For example, ADB computes commitment fees based on a standard
disbursement schedule, which often does not match the proposed
implementation schedule of the implementing agency. During loan
negotiations, implementing agencies should negotiate with ADB
for the adoption of doable and more realistic disbursement schedules.
115.
On the other hand, WB computes on the basis of undisbursed amount.
At the time of appraisal, even if an agency fully meets its disbursement
targets, commitment fees are expected, and can be estimated.
116.
In any case, the possibility of charging commitment fees against
the agency ceilings of implementing agencies may be instituted,
to encourage agencies to be expeditious and efficient in project
implementation.
117.
Different Financing Terms of Projects – Different financing
terms made available by various NG agencies for sub-projects of
LGUs and water districts permit the latter to shop for the best
financing package. As a result, in some cases, LGUs and water
districts withdrew from one project with stiffer financing terms
or greater equity requirements and apply to another with more
attractive conditions. At appraisal, GOP should consider reconcile
lending policies of government financial institutions and the
MDFO.
118.
Multi-Agency Participation in Projects – Projects with multiple
implementing agencies recorded lower indicators than the GOP average.
Such projects require tremendous efforts in coordinating various
participating agencies. Different agencies often differ in their
operational arrangements and procedures, which affect the pace
of implementation. Projects with complicated design involving
many agencies should be avoided or minimized. Packaging and designing
of projects should as much as possible confine scope of activities
to a single agency.
G.
MEASURES FOR 2004 AND BEYOND
As
the government has demonstrated much improved capacity to utilize
ODA, attention should shift to achieving desired project outcomes
and development impact and increasing efficiency in delivering
services by reducing administrative, project management, and consultancy
costs. To sustain improved performance of ODA in the country,
the following measures are recommended:
119.
Strengthen focus on results and outcomes of projects, and their
impact on poverty alleviation and regional development. The NEDA
Board has tasked agencies to monitor results and development outcomes
of projects. The ICC Secretariat should initiate formal review
by ICC of proposed logframes during project appraisal. Capability
building on results monitoring and evaluation (RME) should be
continued.
120.
Improve effectiveness of operationalizing the Medium Term Expenditure
Framework (MTEF) to minimize occurrence of budget issues in projects.
121.
Both implementing and oversight agencies to be involved as early
as project fact finding missions to ensure consistency of projects
with government priorities and avoid instances where preparatory
activities are nullified because projects are later not considered
high priority.
122.
Improve quality at entry of projects. For loans with commitment
fees, loan signing and effectivity should be closely monitored.
GOP should avoid situations when commitment fees are already being
charged (e.g., 60 days after loan signing) but loans cannot be
utilized (i.e., because loan is not yet effective for any reason).
GOP, especially oversight agencies, should also ensure that adequate
preparation has been undertaken prior to loan signing such that
an agency can immediately undertake significant project scope;
slow start in implementation yields higher commitment fees. GOP
should also match projects on the basis of readiness for implementation
with appropriate funding institution; it is desirable that projects
with long preparation required (e.g., feasibility study, detailed
engineering, LGU capability-building, etc.) be matched with loans
with no or very low commitment fees.
123.
Conduct value-for-money and cost-efficiency review for all projects,
and adopt appropriate strategies such as domestic technologies,
skills and services, etc., to reduce cost for non-essentials.
Find ways to cut costs for consulting services. Make use of consultancy
services only when they are really necessary, and not as an automatic
component.
124.
On project design, it is recommended that the sizes of loans especially
for demand-driven or program-type or sector loans be reduced to
more manageable levels, based on experience of loan cancellations
over the years. Likewise, projects with complex procurement design
and organizational setup involving more than one implementing
agency should be minimized. Projects that involve mainly tied
supply of goods and equipment and employ direct payments should
be reviewed thoroughly. For program loans, avoid conditionalities
that require legislative action.
125.
Adapt design of projects with LGU participation to technical and
financial capacity of target LGUs. Revisit the different capacity-building/training
strategies for LGUs with a view to harmonizing initiatives under
different projects, and making them more responsive to actual
needs and capacities of LGUs. Avoid pre-selection of LGUs unless
firm commitments are in place and sanctions for withdrawal or
non-compliance can be enforced; adopt competitive selection to
extent possible. Allow longer lead times for preparation and consultation.
Always require LGU counterpart to ensure ownership, that ODA resources
are used only for priority activities, and cost efficiency. Carefully
review procurement design and flow of funds through MDFO/MFC.
Implement ODA monitoring system for LGUs.
126.
Need to issue guidelines for the newly created MFC to guide implementing
agencies in the budget preparation and execution processes of
ongoing and new projects.
127.
Consider more program/sector type of loans, e.g., Social Expenditure
Management Project (SEMP), for other type of projects. SEMP reimburses
the national government for expenditures made for regular programs
and projects in the General Appropriations Act under the social
sector such as school buildings, textbooks, medicines, among others.
Savings in consultancy services and processing times (procurement
and disbursement) are expected. In this connection, experiences
in implementing Comprehensive and Integrated Delivery of Social
Services, for example, under SEMP and under an investment loan,
KALAHI, should be reviewed.
128.
Consistent with DBCC-ICC approval in principle on 26 June 2002
and again on 3 April 2003 of the policy of the charging of commitment
fees against agency budgets with the objective of making agencies
accountable for the costs of project delays, oversight agencies
should lay down the implementing mechanism. GOP to carefully review
disbursement targets being committed in loan agreements, which
are basis for computation of commitment fees and availment rates.
Other measures that may be considered should aim to control increases
in project costs and ensure efficiency in disbursements and special
accounts through appropriate incentives and penalties. Present
methodologies for estimating overhead costs based on project costs
that may provide skewed incentives to agencies should be reviewed.
129.
Continue to support the Project Implementation Officers (PIO)
system as PIOs have demonstrated capability to move problematic
projects and improve ODA performance.
130.
PIOs to continue to closely monitor procurement activities, institutionalize
internal systems for tracking procurement activities, ensure strict
adherence to timelines, delineate clear lines of responsibilities,
and address systemic bottlenecks. Major infrastructure agencies,
e.g., DPWH, DOTC, NPC, NIA, should adopt ways to further streamline
procurement processes, e.g., through delegation of authority,
reduction of number of layers (e.g., are MANCOM, OGCC reviews
necessary?). To avoid poor performing and unqualified contractors,
agencies should also enforce more stringent pre-qualification
standards, in addition to imposing incentives and sanctions.
131.
The Government Procurement Policy Board (GPPB) to further review
performance of agencies which are observed to be unable to comply
with prescribed timelines, and provide necessary assistance.
132.
PIOs to devote priority attention and ensure high-level decision-making
for right-of-way problems. The role of LGUs in right-of-way acquisition
and resettlement should be reviewed, in order that LGUs can take
greater responsibility for fast-tracking projects in their vicinity,
for example, by generating public support for expeditious ROW
acquisition and resettlement activities, and ensuring that ROW
and resettlement costs do not overshoot initial NG estimates through
appropriate cost-sharing schemes. GOP to work early with funding
institutions to determine mutually acceptable arrangements on
activities specifically covered by guidelines of funding institutions
but funded by local counterpart, e.g., ROW and resettlement. Agencies
should also update their medium-term ROW acquisition plans consistent
with their medium-term program of works for ODA projects, and
be able to get ROW funds sufficiently ahead of start of civil
works.
133.
Agencies to further streamline procedures for document processing
and funds flow within implementing agencies. Continuous training
on procurement and disbursement guidelines for implementing agencies
and LGUs. Delays due to lack of understanding of guidelines especially
by first-time ODA users should be avoided.
134.
DBM issued National Budget Circular No. 485 on 13 March 2003 on
the rationalization of PMOs. The circular provides for the integration
of existing project offices in the regular structure, systems
and functions of agencies and ensure operational sustainability
and alignment of project concerns with overall agency program,
optimum use of resources, strengthening performance monitoring
and accountability, and development and strengthening of in-house
capability. Agencies should prepare their respective PMO rationalization
plans.
135.
Continuously revisit sub-loan features of relending projects to
make them more attractive to end-users, whether industry or LGUs,
e.g., effective interest rates, eligible scope, etc.
136.
GOCCs/GFIs to continue to improve their ODA performance, given
that the fiscal position of the government could constrain NG
agencies.
H. BUDGET OUTLAY AND
REQUIREMENTS (Table 10)
137. Budget requirements of ongoing
FAPs for succeeding years, as submitted by agencies are as follows:
about P42 billion for CY 2004, P63 billion for 2005, P40 billion
for CY 2006, P21 billion for CY 2007, and P14.4 billion for future
years.
I.
PROSPECTS IN 2004
138.
The biggest challenge in 2004 is managing the transitions at NG
and LGU levels after the 2004 elections. Changes in agency and
LGU leaderships have shown significant impact on project implementation,
especially procurement. The smoother the transition, the less
the negative impact on ODA performance.
139.
ODA commitments have been decreasing over the last four years
and it is likely that disbursements from said loans will be decreasing
in the future. Thus, there is need focus on sustaining improvement
in efficiency in ODA utilization for projects. The program loans
portfolio is reduced to a single loan, hence ODA performance will
rely largely on project loans.
140.
Possible Cancellations in 2004 – Partial cancellations of
about US$65 million dollars from nine projects are foreseen in
CY 2004, as a result of reduction in scope of some projects and
foreign exchange movement, etc. (Table 11).
|