I. OVERVIEW
1.
This Review is in compliance with NEDA Board instructions and
RA 8182, as amended by RA 8555, or The ODA Act, which
mandates NEDA to conduct annual reviews of the status of implementation
of all projects financed through Official Development Assistance
(ODA). A report must be submitted by NEDA to Congress on the outcome
of the ODA Portfolio Review.
2.
Pursuant to the ODA Act, the Government uses ODA to achieve equitable
growth and development through priority development projects for
the improvement of economic and social service facilities. As
part of the Review, the consistency of ongoing ODA projects with
the Medium-Term Philippine Development Plan (2004-2010) and the
Medium-Term Public Investment Program (2005-2010) was validated.
3.
In summary, based on several indicators, the countrys ODA
loans portfolio performance dipped in 2004, reversing trends of
improvement in previous years. This is largely on account of the
budgetary issues, the elections in 2004, and delays in procurement
activities. With the Medium-Term Public Investment Program in
place, priority projects identified are intended to be fully supported
by the budget. Moreover, key projects of GOCCs, which encountered
delays in procurement, have now started implementation. Thus,
the ODA portfolios performance is expected to improve again.
4.
In the course of the Review, 29 agencies were met and consulted.
These are : Autonomous Region in Muslim Mindanao Social Fund for
Peace and Development PMO, Bases Conversion Development Authority
(BCDA), Department of Agriculture (DA), Development Bank of the
Philippines (DBP), Department of Education (DepEd), Department
of Environment and Natural Resources (DENR), Department of Land
Reform (DLR), Department of Finance (DOF), Department of Health
(DOH), Department of Interior and Local Government (DILG), Department
of Public Works and Highways (DPWH), Department of Social Welfare
and Development (DSWD), Department of Tourism (DOT), Department
of Transportation and Communication (DOTC), Light Rail Transit
Authority (LRTA), Land Bank of the Philippines (LBP), Local Water
Utilities Administration (LWUA), Metropolitan Waterworks and Sewerage
System (MWSS), National Irrigation Administration (NIA), National
Power Corporation/National Transmission Corporation (NPC/TransCo),
Pasig River Rehabilitation Commission (PRRC), Philippine Economic
Zone Authority (PEZA), Philippine Merchant Marine Academy (PMMA),
Philippine National Oil Company Energy Development Corporation
(PNOCEDC), Philippine Ports Authority (PPA), Provincial
Government of Lanao del Norte (PGLDN), Subic Bay Metropolitan
Authority (SBMA), Supreme Court (SC) and Technical Education and
Skills Development Authority (TESDA).
5.
This report includes a section on procurement activities in ODA
projects. This section will (a) look into the time it takes for
the whole procurement process, from start of tender (or issuance
of bid documents) to the issuance of notice to proceed (NTP);
(b) review compliance of agencies with prescribed timelines in
RA 9184 or the Government Procurement Reform Act, (c) identify
causes of delays, and (d) recommend measures to be undertaken
to streamline the procurement process, or report measures already
put in place by agencies.
6.
As in the previous year, this report discusses, among others,
outputs and accomplishments of completed and ongoing ODA projects,
the ODA portfolio performance using various indicators, commitment
charges paid, and implementation issues encountered in 2004 and
measures to address them.
7.
The report also aims to incorporate the reporting of project outcomes
and impacts as mandated in NEDA Board Resolution No. 3 s. 1999
and supported by NEDA Board Resolution No. 14 s. 1999 [(which
approves the Guidelines Incorporating Results Monitoring and Evaluation
(RME) in the Investment Coordination Committee (ICC) Approval
Process)].
8.
This report is divided into two parts: Part I provides an overview
of the review process and the reports scope and contents
while Part II describes the ODA loans portfolio, and discusses
indicators of portfolio performance, accomplishments and outputs
of completed projects, implementation issues, lessons learned
and implications, future budget requirements of ongoing projects,
and prospects for 2005; and outputs.
II.
ODA LOANS PORTFOLIO
9.
This Review covers 177 active loans with a net commitment of US$10.7
billion, composed of 176 project loans supporting 148 projects,
and one (1) program loan. Project loans accounted for 99% or US$10.5
billion, while program loans, 1% or US$0.2 billion (Annex A-1).
Over the last four (4) years, ODA commitments have been decreasing
as a result of Governments greater adherence to project
quality and fiscal discipline. From a peak of US$13.3 billion
in 2000, ODA loans commitment amounted to US$10.7 billion as of
31 December 2004, which is 6% lower than the 2003 figure and 23%
lower than the 2000 figure.
10.
The concessionality of ODA loans is measured by its grant element.
As of December 2004, the grant element of all ODA loans since
promulgation of ODA Act was 66 percent as computed by DOF. Per
this Act, the weighted average grant element of all ODA at anytime
shall not be less than 40% and each ODA must contain a grant element
of at least twenty-five percent (25%)[1]. The grant element is
the reduction enjoyed by the borrower when debt service payments
(principal and interest) expressed at their present values discounted
at 10% are less than the face value of the loan or loan and grant.
The grant element of ODA loans increased from 53% in 2000 to 62%
in 2003. However, in 2004 a drop by four (4) percentage points
from 62% to 58% was recorded. (Annex A-1A)
11.
Among funding sources, the Government of Japan through the Japan
Bank for International Cooperation (JBIC) remained as the largest
source of ODA loans, accounting for 61% (or US$6.5 billion with
73 loans) of the total ODA, followed by the World Bank (WB) with
13% (or US$1.4 billion with 26 loans) and Asian Development Bank
(ADB) accounting for 11% (or US$1.1 billion with 35 loans). Other
Sources (like Australia, Austria, China, DANIDA, European Investment
Bank, France, Germany, IFAD, Korea, Kuwait, NORDIC Development
Fund, OPEC, Spain and United Kingdom) accounted for the remaining
US$1.6 billion from 43 loans, or 15% of the total ODA loans portfolio.
The amount of assistance from the Other Sources has increased
by US$909 million compared to the 2000 level of US$656 million
(from a share of 5% to 15%).
12.
Across development sectors, the bulk of ODA was channeled to Infrastructure
Development, which received 106 loans with an aggregate commitment
of US$7.3 billion or 69% of the total ODA loans portfolio. Agriculture,
Agrarian Reform and Natural Resources, accounted for 17%, US$1.8
billion from 41 loans. Industry and Services had 5%, US$542 million
from 3 loans, while the Social Reform and Development Sector had
9%, involving US$891 million from 26 loans. In Infrastructure,
Transportation obtained the biggest share of US$5.3 billion (or
51%), followed by Water Resources, US$933 million (or 9%) and
the Energy, Power and Electrification, US$714 million (or 7%)
(Annex A-2). The social reform and development sectors share
in the portfolio increased from 6% in 2000 to 9% in 2004 while
the share of the industry and services sector decreased from 11%
to 5% in the same period.
13.
National Government (NG) agencies and local government units were
responsible for implementing 56% of the ODA project loans portfolio,
involving 116 loans with net commitment of US$5.9 billion. On
the other hand, government-owned and controlled corporations (GOCC)
and government financial institutions (GFI) administered 44% (or
US$4.6 billion) of the ODA project loans portfolio involving 60
loans (Annex A-3). There was a substantial decrease in the share
of NG-implemented projects by four (4) percentage points from
61% in 2003 to 57% in 2004. Conversely, an increase in the share
of GOCCs/GFIs implemented projects from 39% to 43% was noted over
the same period.
14.
ODA loans may be further classified into (a) those that require
budget cover (e.g., those financing projects implemented by line
agencies and some GOCCs like NIA and those with MDFO as conduit),
and (b) those that do not (i.e., those financing projects of GOCCs/GFIs
and the program loans). The former accounts for 66% of the 2004
portfolio, compared to only 53% in 2000 (Annex A-4). The 22 loans
that pass through MDFO comprised 8% of the ODA project loans portfolio
in 2004 and 12% of the budget- dependent portfolio for the same
period (Annex A-5). Meanwhile, the 48 ODA projects with LGU participation
accounted for 18% of the projects portfolio, more or less stable
since 2000 (Annex A-6).
15.
All ongoing projects funded by ODA are supportive of the MTPDP
2004-2010 and are included in the MTPIP 2005-2010, except for
three (3) projects: a) Pasig River Rehabilitation Project (PRRC)
- only the housing component was included and other components
will be included in MTPIP updating; b) Maritime Safety Improvement
Project Phase C - only the budget for GOP counterpart is allocated
(for the buoy base); and c) Selected Airports Project (Tacloban)
- although listed in the MTPIP, it has no allocation for 2005
onwards.
16.
New Loans New loans worth US$733 million, or 7% of the
total commitments, entered the portfolio in CY 2004. These include:
(a) three loans from GOJ/JBIC (US$115 million); (b) three loans
from ADB (US$74 million); (c) three loans from WB (US$75 million);
and (d) one each from Belgium, China, Germany and Korea amounting
to a total commitment of US$469 million (Table 1). The weighted
average grant element of new loans was 64.8%.
17.
Loan Cancellations Partial cancellations of US$204million
were done in 30 loans as follows: (a) ADB, US$65 million; (b)
JBIC, US$91 million; (c) WB, US$28 million; and (d) Other funding
institutions, US$20 million (of which US$19 million is from Germany).
These cancellations were agreed upon with funding agencies due
to: a) excess financing as a result of foreign exchange rate movement;
b) lack of demand for relending; c) reduction in scope of projects;
and d) budget constraints. In the process, these cancellations
will generate savings for the government on commitment fees, in
some cases (Table 2).
A.
DEFINITION OF INDICATORS
18.
Four indicators of ODA absorptive capacity are presented. These
are: (1) disbursement level; (2) disbursement rate; (3) availment
rate; and (4) disbursement ratio. These data on loan utilization
can be used as proxy indicators of the physical performance of
the different programs and projects.
19.
The disbursement level is the actual amount of disbursements (in
dollar terms) from all ODA loans for the period January to December
2004.
20.
The disbursement rate is defined as actual disbursements as a
percentage of target disbursements for a given period. Targets
are set on an annual and quarterly basis, in consultation between
implementing agencies and funding institutions (ADB, JBIC and
WB only). This indicator reflects both on the planning and implementation
capacities of agencies. Very high and very low rates can reflect
poor planning (too optimistic targets or under-targeting) or poor
implementation. Annual targets should be consistent with finishing
a project within its implementation schedule and the loan period.
21.
The availment rate, which has been reported by the NEDA in all
past portfolio reviews, is defined as the cumulative actual disbursements
as a percentage of cumulative scheduled disbursements (references:
loan agreement, credit agreement, appraisal report, supply contracts,
or generated S-curves) reckoned from the start of implementation
of all projects up to December 2004. This captures the historical
performance of a project from start to completion. Backlogs incurred
at the start of the implementation, if not fully recovered, can
pull down the availment rate for the remainder of the project
life. It is imperative that implementing agencies are able to
carefully review the disbursement targets based on aforementioned
references. For ADB, WB and other financing sources that charge
commitment fees, the disbursement targets set at loan signing
give an indication of the commitment fees that may have to be
paid over the life of a project.
22.
Finally, the disbursement ratio is the ratio of actual disbursements
in 2004 to the net loan amount available at the beginning of 2004
plus the amount of new loans that became effective less loan cancellations
during the year. It is the indicator commonly used by the funding
institutions.
23.
The ideal availment and disbursement rates are 100%. On the other
hand, a disbursement ratio in the range of 18-20% is considered
normal, based on assumptions of five-year implementation period
and straight-line schedule of disbursements for a considerably
large and uniformly distributed (in terms of age) pool of projects.
However, disbursement ratios depend on the stage of project implementation;
a 5% disbursement ratio for a project at detailed engineering
stage could be acceptable.
B. PORTFOLIO PERFORMANCE
24.
Disbursement Level. The total ODA disbursements of the country
in 2004 reached US$1.1 billion, compared to US$1.4 billion in
2003, or a decrease of US$314 million or 22% (Annex B-1). Project
loans alone registered only a 5% decrease, from US$1.1 billion
to US$1.0 billion, while program loans posted a 78% decrease,
from US$338 million to US$75 million.
25.
In the case of program loans, GOP was able to substantially comply
with major loan conditionality under the Second Non-Bank Financial
Governance Program II (ADB) resulting in the release of the final
tranche from this loan.
26.
Agencies where significant drop in disbursement levels were noted
are: ASFPD-FMO, BCDA, DENR, DOH, LRTA, PHIVIDEC and PNOC-EDC (Annex
B-2). Reasons cited by the implementing agencies for the decrease
in disbursement levels were: unavailability of counterpart funds
or insufficient budget cover; changes in priorities of LGUs; completion
of project or loan closure; and procurement delays.
27.
All sectors posted decreases in disbursement levels except for
the Industry and Services, and Infrastructure sector which recorded
increase of 31 percent (from US$55 million to US$72 million) and
3 percent (from US$630 million to US$649 million), respectively.
The increase in Industry and Services sector is due to the substantial
increases of disbursements in the DBP portfolio as a result of
the increase in the amount of sub-loans approved such as in the
Industrial Support Services Expansion Project, Credit Lines for
Small and Medium-size enterprises (SME), and Domestic Shipping
Modernization Project II. Meanwhile, the Infrastructure sector
registered an increase due to new investments such as in the NorthRail
Project, Phase 1 Section 1 and LRT Line 1 Rehabilitation II, Modernization
II (Annex B-3).
28.
In general, projects whether they are budget-dependent or non-budget
dependent posted decreases in disbursement levels in 2004 over
the 2003 level, by 2% and 8%, respectively. The share of budget-dependent
projects in terms of disbursements increased by 1.5 percentage
points from 56.8% to 58.3% (Annex B-4).
29.
Projects involving LGUs where MDFO serves as conduit registered
a 22% decrease in disbursement levels from US$106 million to US$83
million (Annex B-5). It may be noted that the reduction of disbursement
is largely due to: a) delayed release of funds in the Third Elementary
Education Project, Secondary Education Development Improvement
Project and Early Childhood Development Project; and b) winding-down
of five (5) projects such as the Regional Municipal Development
Project, Subic Bay Area Municipal Development Project, Agrarian
Reform Communities Development Project, Cordillera Highland Agriculture
Resource Management Project and Mindanao Rural Development Project.
30.
Disbursement Rate. On average, implementing agencies achieved
only 72% of the targeted disbursements of projects supported by
ODA. Across agencies and sectors, disbursement rates vary widely
indicating the need to constantly review the target-setting process
of many agencies (Annexes C-1 and C-2).
31.
On a quarterly basis, disbursement rates in 2004 fluctuated from
one quarter to another, for example, from 91% to 72% to 47% to
72% from the first to the fourth quarters. First quarter performance
has been noted to be driven by JBIC-assisted projects, as the
first quarter coincides with the closing quarter of the JBIC fiscal
year (Annex C-3). Disbursement rates of non-budget dependent projects
improved from 73% in 2001 to 74% in 2002 to 90% in 2003, until
a drop from 90% to 76% was recorded in 2004. Similarly, disbursement
rates of budget-dependent projects were also increasing from 74%
in 2001 to 82% in 2002 to 84% in 2003, but also decreased to 67%
in 2004 (Annex C-4). It may be noted that for non-budget dependent
projects the decrease was due to delayed award of contracts, low
demand from LGUs, low demand for credit, delayed implementation
of contracts/additional works, and delayed payment of progress
billings. For the budget-dependent projects the decrease in disbursement
rate was due to re-enacted budget for 2004, delayed procurement
and delayed payment of progress billings.
32.
Availment Rate. Availment rate in 2004 was 58%, three percentage
points lower than the 61% recorded in 2003 (Annex D-1). However,
it may be noted that only the JBIC portfolio is below the 2004
average availment rate. It may be noted that in JBIC portfolio
cancellations are rare because there are no commitment fees. Since
availment rate is a function of targets in foreign currencies
which are determined as early as the time of the signing of the
loan agreement, the peso equivalent of these targets have increased,
sometimes implying a corresponding increase in physical targets,
and additional budget requirement unless the funds are cancelled.
Backlogs in project startup, if not addressed fully early on,
will adversely affect availment rates until the loan closing date.
(This is also true for other funding institutions).
33.
The social reform and development sector registered an availment
rate of 74%, highest among the different sectors (Annex D-2).
An upward trend has been noted in availment rates of this sector
from 49% in 2001, to 59% in 2002, to 68% in 2003 and to 74% in
2004. On the other hand, the infrastructure sector had a rate
of only 55%, which is three percentage points below the average.
It may be noted that budget constraint, procurement and ROW issues
are prevalent in this sector.
34.
Disbursement Ratio. The average disbursement ratio for the three
biggest portfolios was 16%, three percentage points lower than
the 19% recorded in 2003 (Annex E-1). ADB recorded a 24.5% disbursement
ratio, WB 18.5%, while JBIC registered 12.1%. Again, it may be
noted that partial loan cancellation is rare in the JBIC portfolio
because no commitment fees are charged for undisbursed amounts.
It may be recalled that funding institutions called on GOP to
raise its disbursement ratio to 20% by 2004 during the 2002 Consultative
Group Meeting.
35.
Loan Extensions. Seventy-six loans worth US$3.6 billion or 34
percent of the ODA portfolio, including 38 loans which closed
in 2004 (of which 11 loans were not fully availed) amounting US$1.4
billion, were on extended periods of 2.0 years average beyond
their original loan closing dates (Table 3). This is higher than
the 66 loans reported in 2003. Of the 38 ongoing loans which have
exceeded original duration, 19 loans require extensions of more
than one year, while 19 loans require less than a year.
36.
Additional Budget/Funding Requirements. Thirty-one projects will
require additional budget/funding (Table 4) with an aggregate
amount of about P41 billion. Five (5) of these projects with increases
in cost were approved by the ICC in 2004.
37.
In general, the following are the justifications given by IAs
for the additional budget requirements: (a) change in scope/additional
works; (b) increase in right-of-way (ROW) acquisition cost; (c)
high bids; (d) claims for price escalation; and (e) foreign exchange
rate movement.
38.
Commitment Fees. For the ongoing projects, cumulative commitment
fees paid by the government to ADB, WB and other funding institutions
as of December 2004, amounted to US$48.8 million. In 2004 alone,
US$7.5 million was paid in commitment fees. Among national government
agencies, commitment fees paid by GOP for DPWH and DA projects
were US$1.2 million and US$0.8 million, respectively. Among GFIs,
DBP and LBP paid commitment fees of US$0.3 million and US$0.4
million, respectively. (Annex F-1)
C.
ACCOMPLISHMENTS AND OUTPUTS OF PROJECTS
39.
Of the thirty-eight loans closed in CY 2004, twenty-eight loans
amounting to US$1.2 billion were reported as closed/fully availed
during the year (Table 5) consisting of: ten loans from ADB (US$255
million); five loans from GOJ-JBIC (US$357 million); four loans
from WB (US$224 million); two loans from Spain and France (US$22
million and US$33 million, respectively); and one each from Austria,
Australia, EIB, OPEC and UK (a total of US$293 million).
40.
At least 12 loans were closed in 2004 with incomplete project
outputs. These loans were : a) Land Administration and Management
Project (DENR/WB) ; b) Presidents Bridge Program II (DILG/Austria)
; c) Tulay ng Pangulo sa Barangay (DPWH/UK); d) Third Airports
(DOTC/ADB) ; e) Telepono Sa Barangay 2 (DOTC/France) ; f) Global
Maritime Distress Signal System (DOTC/France) ; g) LGU Private
Infrastructure Development Facility (LBP/ADB) ; h) Provincial
Cities Water Supply Project IV (LWUA/JBIC) ; i) Expansion and
Rehabilitation of Baguio Water System (LWUA/Australia); j) Small
Towns Water Supply Sector Project (LWUA/ADB) ; k) Malitubog-Maridagao
Irrigation Project (NIA/JBIC); and l) Rural Water Supply and Sanitation
Project (DPWH/DILG/DOH/ADB).
41.
The reasons cited by implementing agencies for the incomplete
project outputs were: a) budget constraints; b) legal and technical
issues; c) lack of LGU counterpart funds; d) right-of-way acquisition;
and e) project design. To complete the project outputs of said
projects, the implementing agencies propose: a) the use of agency/local
government/corporate funds to complete remaining project activities;
and b) the preparation of a second phase of the project to finance
the remaining requirements. (Details in Table 5-A)
Completed
Projects/Closed Loans (Table 6)
Infrastructure
42.
Under the Second Mandaue-Mactan Bridge Project Phase II, accomplishments
include: four (4) lane roadway (4.464 kilometer) and pre-stressed
concrete bridge with a length of 319 meters over Mananga River.
Travel time from southern to northern Cebu is cut by approximately
one hour as this bypasses the central business district of Cebu
City. . Meanwhile, under the Tulay ng Pangulo sa Barangay, construction
of 32 Tulay Ng Pangulo sa Barangay with a total length
of 978 lineal meters and 142 Tulay Ng Pangulo sa SZOPAD/Mindanao
with a total length of 2,778 lineal meters were completed. These
projects were able to deliver on its objective of supporting the
growth of agricultural, industrial, fishing, commercial and tourism
areas by providing a faster, safer and more reliable road network.
43.
For Rural Water Supply and Sanitation Project, 5,966 Level I water
supply and 61,235 sanitation facilities were constructed/ rehabilitated,
and 4,172 barangay water supply associations were formed/organized
to provide level I (point source) water supply and sanitation
facilities to 20 Social Reform Agenda priority (poor) provinces.
44.
As regards the Metro Cebu Development Project III (Cebu South
Reclamation), completion of the physical activities for the additional
works (Stage I-1 for road network, water and power facilities
and other support activities) would further enhance the saleability
of the reclamation area.
45.
Under the Leyte-Bohol Interconnection Project, 115 kms 138/69
kv T/L and 54 kms 500 kv T/L were energized. Likewise, 88 kms
230 kv T/L under the Luzon Grid Transmission Project were energized.
For the Power Transmission Reinforcement Project, erection and
installation works of 71 steel towers and 22 steel poles were
completed to meet future demands for adequate and reliable power
supply in selected areas.
46.
For the Small Towns Water Supply Sector Project, completion of
the construction activities in 97 Water District (WD) subprojects
(with a total production of 24,000m3/day for 85,000 service connections)
would provide potable water to 500,000 beneficiaries and reduce
non-revenue water by 21%. Under the Provincial Cities Water Supply
Project IV, water supply facilities were completed in Masbate-Mobo
(to benefit 42,000 residents of 18 barangays including the town
proper of the two municipalities), Tarlac (to benefit 145,242
residents of 31 barangays including the city proper) and Bacolod
City (to benefit 292,913 residents of 25 barangays including the
city proper).
47.
Under the Nationwide Air Navigation Facilities Modernization Project
Phase III, civil works and installation of equipment for the power
supply system and alternating current (AC) were completed in the
remaining airport site of Masbate (out of 25 project sites). For
the Davao International Airport Development Project (which aims
to provide safety and security to air transport commuters), the
completed modernization and rehabilitation works included the
following: the landing strip of the existing runway; dual access
taxiway; new passenger terminal; cargo terminal; and airlifting
and air navigation facilities.
48.
For the ADB-assisted Philippine Regional Municipal Development
Project, completed facilities included: Puerto Princesas
bus and jeepney terminal and motorpool equipment shed; Tagbilarans
motorpool equipment shed and delivery of solid waste management
(SWM) equipment; and Iligan Citys drainage improvement,
bus and jeepney terminal and widening of the national road (Junction
Roxas and Quezon Avenue) and the Mandulog Bridge.
Agriculture,
Agrarian Reform and Natural Resources
49.
Under the DENRs Land Administration and Management Project
(LAMP), 504 free patents were issued/registered, 637 completed
patent applications were submitted to the Registry of Deeds (ROD)
for registration, 497 Cadastral Index Map (CIM) sheets were produced
and 73,291 parcels were plotted. The One-Stop-Shop (OSS) operation
and training manuals were produced and a procedure for the detection
of fraudulent and fake titles including documentation of the procedures
in Judicial Titling was developed. The project was also able to
establish the Barangay Advocacy Group (BAG) and Barangay Integrated
Land Information System (BILIS), and dissemination of information
to stakeholders and general public was facilitated.
50.
The ADB-assisted Cordillera Highlands Agricultural Resources Management
Project completed the following: maintenance of 3,215 hectares
and protection of 6,560 hectares of established plantations, and
monitoring and evaluation of activities of NGOs regarding inventory
assessment of established plantations to increase the disposable
incomes of small farm-holder families in the covered area.
51.
For the Grain Sector Development Project, 3 irrigation systems
and 15 Agrarian Training Institute (ATI) centers were rehabilitated,
4 techno-demos were conducted, 44 farmer field schools were established
and several trainings conducted, and the Bureau of Agrarian Statistics
(BAS) local area network was operationalized. Meanwhile, under
the Mindanao Rural Development Project, rehabilitation of 145
farm-to-market roads (FMR) subprojects (with total length of 687
km), 9 one-lane bridges (with total length of 175 linear meters),
28 units of water supply system/spring development (Level II),
and rehabilitation of 43 irrigation projects (with a total service
area of 5,791 ha) were completed. The 1,583 investment community-based/small
infrastructure projects with total fund release of P197 million
(benefiting 37,779 households as economic investment projects
and 16,818 individuals as actual users of small infrastructure
projects) were also implemented. The project was also able to
assist in the preparation of 1,416 barangay development plans
(BDPs), integration of 1,341 BDPs into municipal development plans
(MDPs), and integration of 55 MDPs into provincial development
plan and establishment of 64 technodemo farms in cooperation with
municipal LGUs.
Social
Reform and Development
52.
Under the SZOPAD Social Fund, 250 of the completed 320 subprojects
(includes classrooms, health centers, madrasah or muslim school,
etc.) were officially turned over to the beneficiary communities
to improve access to basic infrastructure and services in depressed
areas and communities, provide livelihood and employment opportunities
for disadvantaged groups. Also completed was the institutional
strengthening mechanism for planning, implementation and monitoring
of the development strategy for the SZOPAD.
53.
For the Upgrading of the Zamboanga City Medical Center, various
medical and technical equipment (computers) were turned over to
the Zamboanga City Medical Center, medical staffs underwent orientation
and demonstration on the various equipment, and non-medical staffs
were trained on the maintenance of the equipment which resulted
in the availability of improved/better health and medical services
and facilities to the people of Zamboanga City.
54.
Meanwhile, under the Upgrading of the Medical Equipment of Department
of Emergency Medical Services (DEMS) of PGH, all the equipment
delivered (5-9 container vans and other medical equipment) would
be helpful in reducing the loss of valuable human lives by improving
the responsiveness, capability and quality of DEMS to deliver
emergency care at any given circumstances. As regards the Hospital
Development Project, 75 hospitals/health centers nationwide were
provided with various medical equipment and supplies.
55.
For the Integrated Community Health Services Project, 150 health
facilities in four (4) provinces (Apayao, Guimaras, Kalinga and
Palawan) were constructed, critical health systems in 4 provinces
such as health service planning system, health care financing
system, health and management information system, hospital operations
and management system, and human resources development system
were designed and implemented, and Simplified Rural Health Module
and referral system was developed.
56.
Under the Upgrading of the Eulogio Rodriguez, Sr. Memorial Hospital,
various medical equipment were provided to the hospitals
major units such as radiology section, intensive care unit (ICU),
out-patient department (OPD), including the laboratory, dental,
and ophthalmology units.
Industry
and Services
57.
The ADB-assisted LGU Private Infrastructure Project Development
Facility which provided financial assistance to LGUs for project
development, completed feasibility studies (F/S) for only two
(2) subprojects (i.e. Davao del Norte Integrated Water Resource
Development Project and Modernization of Olongapo City Public
Utilities Department).
Ongoing
Projects
Infrastructure
58.
Under the roads and bridges sub-sector, overall 104 bridges were
constructed/repaired/retrofitted and 267 kilometers of concrete
pavement were completed. These included the rehabilitation of
the San Juanico Bridge in Samar and Leyte (2.79 kms), Calbiga-San
Juanico Bridge Section in Samar and Leyte (46.24 kms) under Arterial
Road Links Development Project III, and the Tabon-Tabon-Sibagan-Bayugan
Section (34.14 kms) and Tagum-Carmen Section in Davao del Norte
(12.05 kms) under PJHL Mindanao Section Rehabilitation I.
59.
Under air transport sub-sector, rectification works on the runway
(asphalt overlay) for Tacloban airport were completed and all
equipment for both Tacloban and Bacolod airports were delivered,
inspected, and accepted under Selected Airports Phases I and II.
For the Laguindingan Airport Project, site acquisition and perimeter
fencing were ongoing.
60.
For the power sub-sector, all equipment and materials were delivered,
and operational testing is ongoing under the Wholesale Electricity
Spot Market (WESM) component of the Electricity Market and Transmission
Development Project.
61.
In the water resources sub-sector, construction of the following
facilities were completed: (i) 29 on-site sewage treatment plants
in 21 densely populated residential areas (Manila Second Sewerage
Project); (ii) two pumping stations and two floodgates (Metro
Manila Flood Control ProjectWest of Mangahan Floodway);
and (iii) Hector Mendoza Bridge (Agno River Flood Control Project
Phase II-B). in addition, dredging and Pilot Channel Excavation
at Pasac Delta Area and Third River were also completed under
the Pinatubo Hazard Urgent Mitigation Project II.
Agriculture,
Natural Resources and Agrarian Reform Sector
62.
Under Agrarian Reform Communities Project, about 533 kms farm-to-market
roads (FMRs) were constructed/rehabilitated, 856 hectares of agricultural
land were provided with irrigation water, and 45 units of potable
water supply systems were constructed. For the Mindanao Sustainable
Settlement Area Development Project, construction of 4.67 kms
FMRs and 18.80 lm bridges were completed while 15 FMRs (53.092
kms), one potable water supply system, four multi-purpose buildings
and 6 school classrooms are still ongoing.
63.
NIA accomplished the following activities: provided irrigation
to 33,322 hectares of new areas and rehabilitated 129,248 hectares
existing irrigation systems; completed irrigation management transfer
(IMT) consultations/negotiations for 18 national irrigation systems
(NIS) where improvement works were being undertaken; organized
65 new irrigators associations (IAs); strengthened the capacity
673 existing IAs; signed 222 new Memorandum of Agreements (MOAs)
between IA and NIA; renewed 810 MOAs; and trained 23,500 farmers.
Industry
and Services
64.
Under the LGU Support Credit Program, 37 LGU projects under the
following categories were completed namely: two (2) for housing
and health, twenty-six (26) for water supply/flood control/sanitation
and nine (9) for forestry and sewerage/solid waste. For the Third
Rural Finance Project, 121 subloans amounting to P2.105 B were
provided to large and small and medium enterprises (SMEs) for
the year, and 13,054 cumulative jobs were created.
Social
Reform and Development
65.
Nationwide implementation of the Fixed Dose Combination to address
tuberculosis has commenced with the award of the contract for
the supply of TB drugs amounting to US$7.11 million (66% of the
US$10.82 million actual requirement), and about US$0.97 million
(64%) worth of vaccines for the rabies control program were contracted
and delivered under the Social Expenditure Management Project,
Phase II. Meanwhile, under the Investment Component of the Metro
Manila Air Quality Improvement Sector Development Program, the
equipment were procured and installed at various air public health
monitoring sites in Metro Manila, and the manuals on Health Risk
Assessment, Epidemiological Study on Sentinel Communities and
health Risk Perception Survey were completed and disseminated
to different stakeholders including international agencies (ADB,
WHO, etc.).
66.
Under the Social Expenditures Management Project II, 1,271 classrooms
were constructed/rehabilitated, 1,411 classrooms repaired and
maintained and 11,078,634 copies of textbooks and teacher manuals
of different titles were delivered. In the Secondary Education
Development and Improvement Project, 185 classrooms were constructed,
1.4 million textbooks and 48,782 teachers manuals were delivered
and supplied. For the Third Elementary Education Project, 4,977
classrooms were constructed/rehabilitated; 61,306 teachers, district
supervisors and school managers attended various division-based
trainings; and more than 1.3 million instructional materials and
textbooks were delivered.
67.
Under the KALAHI Project, out of the 740 approved sub-projects,
317 were completed as follows: 83 potable water supply systems,
63 farm-to-market roads; 25 schoolbuildings; 33 day-care centers;
41 health stations; multi-purpose buildings; and 64 electrification,
corn mill, pump boat, etc.
D.
KEY IMPLEMENTATION ISSUES
68.
Budget Cover. The reenacted General Appropriations Act (GAA) provided
P33.5 billion for foreign-assisted projects (FAPs) in 2004, 15%
lower than the proposed budget of P39.4 billion as reflected in
the 2004 Budget of Expenditures and Sources of Financing (BESF),
and seven (7) percent lower than the 2003 actual budget of P 35.9
billion. The capital outlay portion of the budget for ODA projects
in 2004, amounting to P29 billion, accounted for 31% of the P93
billion total NG capital outlays. The total NG budget in 2004
was P861.6 billion.
69.
The 2004 reenacted budget affected implementation of most ongoing
projects particularly those with increasing budget requirements,
and new projects (e.g., Laguna de Bay Institutional Strengthening
and Community Participation Project, General Santos Fishport Complex
Expansion/Improvement Project, ARMM Social Fund for Peace and
Development Project, Arterial Road Bypass Project Phase I-Plaridel
and Cabanatuan and Central Mindanao Road Project.)
70.
Fifteen out of 19 budget-dependent implementing agencies/units
reported budget issues: projects not in the GAA, projects which
have unprogrammed budgets in the GAA, projects which have physical
accomplishments whose financial requirements exceeded the available
budget cover for the year, and projects using MDFO as conduit.
71.
Eight (8) implementing agencies reported that contractors and
consultants have unpaid billings of at least P4.6 billion in the
JBIC portfolio. DPWH and LRTA reported that unpaid claims of their
contractors and consultants in the JBIC portfolio as of February
2005 amounted to P1.6 billion and P1.2 billion, respectively.
72.
The limited budget provided for implementation of some ODA projects
in the past few years led to extension of implementation schedules
in projects of DPWH, DILG and DOTC. This is expected to result
in cost overruns.
73.
Under existing grant/loan agreements with GOJ-JICA and GOJ-JBIC,
local taxes levied on contracts funded by Japanese loans and grants
cannot be charged against the proceeds of GOJ-JICA/JBIC assistance.
These taxes are advanced by contractors subject to reimbursement
by the government agency. However, in a number of agencies, said
amounts to reimburse the VAT paid by the contractors were not
covered by appropriations. As of December 2004, a total of P371
million worth of taxes have not been reimbursed to these contractors
and consultants.
74.
Procurement. Of the 32 civil works, 24 consulting services and
20 goods contract packages reviewed, it was noted that there is
a wide range of procurement periods. Agencies reported that procurement
activities from submission of bids to issuance of notice to proceed,
takes between 2.5 months to 28 months versus the prescribed timeline
of 3.2 months per Republic Act 9184. A number of GOCCs (BCDA,
LRTA, PNOC-EDC and SBMA) encountered delays in procurement with
contract amounts ranging from P3.7 billion to P21 billion, resulting
in inability to meet performance targets.
75.
In general, the reasons for procurement delays were: (a) failure
in bidding/rebidding of contracts (DILG, NPC/TransCo, DA/BFAR,
NIA, PRRC, and DOTC); (b) complaints filed by losing bidders (DPWH);
(c) lengthy review process (MWSS and DOTC/LRTA); (d) difficulty
in compliance with documentation requirements; (e) changes in
project scope (BCDA); and (f) changes in leadership.
76.
Some improvements in procurement periods of agencies were noted.
In DPWHs procurement of civil works, the average number
of months from submission of bids to issuance of NTP decreased
from 9.44 months in 2003 to only 6.4 months in 2004. In LWUA,
procurement timeline for civil works decreased from 12 months
to 3.69 months. The experience of the DPWH in the Sustainable
Environmental Management in Northern Palawan Project is worth
highlighting as the procurement process from submission of bids
to issuance of NTP took only 3.6 months, very close to the 3.2
months prescribed timeline in RA 9184.
77.
As regards projects funded by GOJ-JBIC Special Yen Loans, the
agencies were requested to document their experiences with respect
to procurement process with respect to the requirement for 50%
Japanese content and limited to Japanese contractors only, for
the New Iloilo Airport Development Project (DOTC), 2nd Magsaysay
Bridge and Butuan Bypass Project (DPWH), Northern Luzon Wind Power
Project (PNOC-EDC) and Subic Clark - Tarlac Expressway
Project.
78.
MDFO/MFC Transition. Executive Order No. 252 on the conversion
of the Municipal Development Fund Office (MDFO) to Municipal Finance
Corporation (MFC) was issued in December 2003, and MFC was made
an affiliate of the Land Bank of the Philippines in June 2004.
In 2004, the reenacted GAA did not include appropriations for
MDFO relending to LGUs. As a result, some projects using the MDFO/MFC
conduit were affected.
79.
The transfer of national government grants to LGUs with ongoing
projects continued to be a problem even if the NG budget is available,
because of the absence of a mechanism acceptable to both MDFO
and DBM. Joint recommendation by DBM and MDFO of the feasible
mechanism is awaited.
80.
LGU Participation. ODA projects with direct LGU participation
accounted for 18 percent of the portfolio. The lack of LGU equity
is a major problem. A number of local government units (LGUs)
withdrew participation in the projects due to the NG-LGU cost
sharing scheme for LGU-devolved programs. An example is the Agrarian
Reform Communities Development Project of the Department of Land
Reform wherein out of five (5) approved subprojects only one (1)
was implemented because of the minimum 50% required LGU counterpart.
As of December 2004, five (5) LGUs formally withdrew their applications
and 12 LGUs have not submitted any subprojects for approval for
the past two (2) years.
81. The lack of LGU equity also affected implementation of the
Rural Water Supply and Sanitation Project V of the DILG in the
provinces of Mindoro Oriental and Nueva Vizcaya. Requisite project
preparatory activities particularly on capacitating LGUs took
longer than expected. In some cases, this resulted in the reallocation
of programmed LGU to other LGU priorities.
82.
The limited technical capacity of LGUs under DOFs Local
Government Finance and Development Project likewise delayed implementation.
Some LGUs had difficulties in complying with pre-qualification
requirements, documentary requirements for clearances, and preparation
of detailed engineering designs. In addition, there is competition
posed by other available LGU financing facilities (GFIs and NGAs-led).
83.
Right-of-Way Acquisition. Many agencies have reported positive
experiences with RA 8974 commonly known as the Expropriations
Law. Notable is the experience of BCDA in acquiring a total
of 645 hectares of land in 2.7 years under the Subic-Clark-Tarlac
Expressway Project. BCDA attributes the expeditious acquisition
of right-of-way to: a) constant follow-up with the courts by competent
BCDA lawyers of their expropriation cases; b) availability of
funds for payment to landowners; and c) incentives to BCDA ROW
acquisition teams.
84.
A major problem in land acquisition is the availability of funds
for payment to landowners. The law requires the implementing agency
to deposit the payment of 100% BIR zonal value or proffered value
of the property to be acquired with a government bank after filing
the petition on eminent domain case. With budget constraints,
the ROW acquisition requirements may not be fully supported by
the implementing agencies.
85.
However, some agencies still encountered difficulties in ROW acquisition.
LWUA had difficulty in securing DPWH/LGU excavation permits for
its water supply projects. NIA and DPWH encountered problems in
processing claims of landowners without proof of ownership. PRRC
experienced problems with ROW acquisition because land donation
takes a long time.
86.
As in prior years reviews, some agencies reported that differences
in guidelines of GOP and funding institutions contributed to delays
in ROW acquisition in the Sixth Road Project and Third Airport
Development Project.
87.
Increase in Costs. Thirty-one (31) projects in the ODA loans portfolio
were reported by implementing agencies to involve cost increases
amounting to P41 billion (Table 4). Of this amount, P10.6 billion
(25%) was approved by ICC in 2004 and early 2005, P15.7 billion
(37%) are either under evaluation by the ICC Secretariat or for
ICC approval, and P16 billion (38%) are still for submission to
ICC by the concerned agencies (but initial estimates were submitted
to the Secretariat).
88.
By implementing agency, the DPWH accounts for the biggest share
of cost increase with 80% or P33 billion (for 21 projects) followed
by NIA and DOTC with 5%, PRRC with 4%, PNOC and TESDA with 2%
each, and NPC and PMMA with 1%.
89.
Half of these cost increases or P21 billion (for 21 projects)
occurred in projects funded by GOJ-JBIC, followed by ADB with
P11 billion or 27% (4 projects), and World Bank with P7 billion
or 16% (2 projects). It may be noted that GOJ-JBIC accounts for
61% of the total ongoing ODA loans portfolio, followed by World
Bank with13% and ADB with 11%.
90.
2004 Elections. There was a slowing down in approval of sub-projects
involving LGUs as many local officials postponed loan negotiation/signing
after the elections. Likewise, some ROW acquisition and relocation
activities were postponed after the elections.
91.
Changes in Leadership. Changes in LGU leadership as a result of
the elections could mean changes in LGU priorities and project
management teams and could substantially delay project implementation.
Affected projects include the Water Districts Development Project
and Rural Water Supply and Sanitation Project.
92.
Changes in heads of agencies have likewise been observed to have
significant impact on implementation of ODA projects. This resulted
in delays in award of contracts, because of repeated reviews of
contracts for due diligence, or in certain cases, even changes
in project design. In the case of TESDA, there was a change of
Director-General twice in 2004, and the change in leadership eventually
led to the appointment of new project managers of all ongoing
projects.
93.
Credit/Relending Facilities Issues. Financial indicators of GFIs
(DBP and LBP) showed signs of recovery. Disbursement levels increased
from US$157 million in 2003 to US$171 million in 2004. Availment
rate and disbursement ratio increased by eight (8) and five (5)
percentage points, for the same period, respectively.
94.
But in general, GFIs still claim that demand for credit remained
low. They attribute the low demand to the wait-and-see attitude
of the private sector with respect to the investment climate,
selective lending to big projects of the Private Financial Institutions
(PFIs) in order to minimize risks, and the limited capability
of some conduit rural banks to package medium- to long-term loans.
95.
EO 138, issued in 1999, directs government entities involved in
the implementation of credit programs to adopt the credit policy
guidelines formulated by the National Credit Council. It specifies
that interest rates charged for government credit programs should
not be lower than the prevailing market rates. However, some wholesale
lending programs charge below market rate thereby affecting other
wholesale lending programs. A policy issue that needs to be clarified
is on the concessionality of available ODA loans, in particular
the relending facilities of JBIC and KfW compared to other sources.
It is therefore necessary to define the policy on who should benefit
from the greater concessionality of some ODA loans: NG, GFIs or
the borrowers?
96.
While EO 138 limits GFIs to providing wholesale funds to PFIs
(except in sectors not adequately served by the PFIs), GFIs continue
to perform both wholesale and retail lending operations. On its
part, DBP explained that its charter states that as a development
bank it can do both. DBP reported that they have been efficient
in marketing both lending windows and that they usually apply
retail lending programs to projects with long gestation periods.
97.
Coordination between MMDA and DPWH. Metro Manila Development Authority
raised issues on the design or implementation of certain road
projects in Metro Manila such as the MM Interchange Construction
Project V, and the EDSA Pavement Rehabilitation Component of the
Metro Manila Air Quality Project, which led to the delay of these
projects. For the MM Air Quality Project, MMDA in April 2005 concurred
with the rehabilitation of the road section between Buendia Avenue
to Kamias. In the case of MM Interchange V, DPWH may cancel the
loan.
98.
Legal Cases. On the Agno River Flood Control Project Phase
II, the case alleging that there was irregularity and anomaly
in the bidding and award of the contract to the lowest bidder
remained pending since 2002 with the Supreme Court. In April 2005,
the SC upheld the dismissal of the petition/complaint and clarified
that the advisory made by the Regional Court to DPWH that it must
seriously consider awarding to the third lowest bidder has no
binding/legal effect.
99.
Regarding the Mindanao Container Terminal Project, a TRO was issued
by a RTC in April 2004 for the PHIVIDEC Industrial Authority to
cease and desist from engaging in cargo handling operations at
the Mindanao Container Terminal for cargoes not owned or consigned
to the locators in the PHIVIDEC Industrial Estate. In January
2005, the Court of Appeals allowed PHIVIDEC to operate.
E.
MEASURES TAKEN TO IMPROVE PORTFOLIO PERFORMANCE IN 2004
100.
To provide the development framework of the government in support
of the 10-point agenda and the National Development Agenda, the
President issued Memorandum Order No. 156 Approving and Adopting
the Medium-Term Philippine Development Plan 2004-2010 and its
accompanying Medium-Term Public Investment Program (MTPIP) 2005-2010
on 13 December 2004. ODA priority projects included in the 2004-2010
MTPDP/MTPIP will be implemented with full budgetary support. Along
this line, DBM issued in August 2004, a programming and budgeting
guideline for 2006-2010 containing the policies for consideration
in the formulation of the MTPIP and future budgets.
101.
To ensure multi-year budgetary support to foreign-assisted projects
(FAPs), DBM issued Circular Letter No. 2004-12 on 27 October 2004
on providing a Multi-Year Obligational Authority (MYOA) to agencies
that voluntarily commit to give priority to and include annual
budgetary requirements of projects whose funding strategy indicates
that the annual budgetary requirements of FAPS may be accommodated
within their annual budgetary ceiling over a period of time. Under
the multi-year contract (MYC) to be entered into by the agencies,
the liability of the government to liquidate obligations shall
be limited only to the extent of the programmed appropriation
released for the purpose. The agency shall commit to include the
funding requirements for the remaining portions of the contract
in its annual budget proposals until the project is completed.
102.
In line with the decentralization policy of GOP, the Investment
Coordination Committee (ICC) and the Development Budget Coordination
Committee (DBCC) amended the policy on national government (NG)
assistance to devolved activities in a memorandum dated 20 August
2004. The NG shall no longer provide grant/subsidy to devolved
programs, activities and projects (PAPs). In cases where LGUs
would need additional resources, they can avail of loans from
the Municipal Finance Corporation (MFC) or other government financing
institutions (GFIs). This policy shall be applied to all proposed
PAPs with budget implications starting 2005.
103.
DPWH likewise issued Department Order No. 203 which requires all
bids/financial proposals under foreign-assisted projects to be
submitted in Philippine pesos. It also requires that all contract
prices be dominated and payable in Philippine pesos only. It aims
to reduce the vulnerability of project cost of foreign exchange
movements. As this order has been contested by funding institutions,
further amendments are expected to define specific items eligible
for foreign exchange payment.
104.
To ensure efficiency in the design and implementation of foreign-assisted
projects given the funding constraints faced by the government,
DPWH issued Department Order (DO) No. 204 on 28 October 2004 prescribing
limitations on variation orders (VOs) for civil works contracts
that are still to be advertised for bidding or negotiated. DO
204 limits the cumulative amount of VOs to not more than 10% of
the original contract cost, provided that the sum of the said
cumulative VOs and the original contract cost shall not exceed
the Approved Budget for the Contract (ABC), as applicable.
105.
Project Implementation Officers (PIO) continued to keep close
supervision over ODA project implementation. PIOs are senior officials
(of Undersecretary or Assistant Secretary rank) designated in
all agencies implementing ODA-funded projects. Their main responsibilities
are to lead the agencies in implementing catch-up programs for
delayed and slow-moving projects, to closely monitor progress
of implementation and to coordinate with concerned agencies to
resolve bottlenecks. The PIOs together with oversight agencies
met quarterly in 2004 to address issues affecting project implementation,
share good practices, and be apprised of recent policies and procedures
on ODA.
106.
In the preparation of the 2005 budget, DBM instructed agencies
to focus existing resources on the core functions of the agency.
Programs and projects which are no longer relevant to their major
final outputs (MFOs) must be eliminated. DBM also instructed the
agencies to prioritize funding commitments for ongoing and newly
approved FAPs in accordance with the approved budget strategy.
107.
To enable greater participation of Filipino constructors and consultants
in foreign-assisted infrastructure projects, EO 278 was issued
by the President on 2 February 2004 prescribing guidelines for
project loan negotiations and packaging of government foreign-assisted
infrastructure projects. The EO provides, among others, that large
government infrastructure projects shall be packaged into separable
work components without sacrificing the technical integrity of
the structure and should take into account Filipino capabilities.
Complex and/or multi-disciplinary infrastructure projects requiring
varied competencies shall also be packaged into separate work
components. In the loan negotiation, the government panel shall
ensure that the loan agreement does not contain provisions which
discriminate against Filipinos and limit their participation in
the project.
108.
On procurement, the harmonized bidding documents for national
bidding have been completed; common training design for the regions
were completed and made available through State Universities and
Colleges (SUCs) nationwide; and agency procurement manuals were
completed and for rolling out to all agencies in 2005.
109.
Upon recommendation of the DBM to the President in a memorandum
dated 2 November 2004, the P344.331 million VAT advanced by Japanese
contractors and consultants will be reimbursed within three (3)
years beginning 2005 for the national government agencies and
five (5) years for the Benguet Provincial Government. This will
include settlement of unpaid VAT up to Dec. 31, 2003 for GOJ-JICA-assisted
projects. It was agreed that for 2004 onwards, the implementing
agencies will regularly include in their budget request an amount
for VAT payment. As reported by DBM, P219 million or 59% of the
outstanding VAT of P371 million is programmed for payment in 2005,
and as of May 2005, Special Allotment Release Order (SARO) amounting
to P191 million was already released to DepEd, DOH and DPWH for
VAT payments. In order to address the VAT problem, a steering
committee was formed , chaired by DOF and composed of representatives
from DFA, DBM, NEDA, Embassy of Japan, JBIC and JICA.
110.
The ICC approved restructuring in the following projects: a) loan
extensions (for more than one year7 projects: Expansion
of Dual Education and Training, Domestic Shipping Modernization
II, Sixth Road, Tiwi and Makban Geothermal Power Plant Partial
Rehabilitation, Fisheries Resource Management, and Batangas Port
Development II), and for a year or less--2 projects: (Provincial
Cities Water Supply IV, and Credit Line for SMEs); b) change in
scope of 2 projects (Southern Mindanao Integrated Coastal Zone
Management, and Batangas Port Development II); c) increase in
cost of 5 projects (Expansion of Dual Education and Training,
Upgrading of the Philippine Merchant Marine Academy, Sixth Road,
Power Transmission Reinforcement-Calamba Tower 50-Binan 230 kV
T/L Component, and Credit Lines for SMEs); and d) full/partial
cancellation for 4 projects (Expansion of Dual Education and Training,
Maritime Safety Improvement IV, Fisheries Resource Management,
and Marine Disaster Response Management, and Marine Disaster Response
and Environment Protection System).
111.
The revised ICC guidelines was adopted in August 2004 to help
ensure the timeliness of the ICC review and approval process.
The updated guidelines was posted in the NEDA website www.neda.gov.ph
for greater transparency of ICC action and to facilitate public
access to information.
112.
GOP continued to adopt budget-support types of loan such as the
Diversified Farm Income and Market Development Project of the
Department of Agriculture (DA), after the experience with Social
Expenditure Management Project (SEMP). Loan funds would be used
to support core functions of an implementing agency. Strengthening
effectiveness of an agencys public investments and interventions
is envisioned without increasing budgetary requirements.
MEASURES
FOR 2005 AND BEYOND
113.
Improve focus on achieving results; for new projects, ensure baselines
are established at first year of implementation. It is also important
that annual performance indicators and targets be established
and agreed upon among the oversight, implementing and funding
agencies at project start-up.
114.
Establish formal monitoring and evaluation mechanisms with Other
funding institutions. Moreover, there is need to clarify implementation
protocols at the time of loan negotiations. Some delays in project
implementation were attributed to unclear procedures of some funding
institutions.
115.
Devote full attention to startup operations of new projects.
The startup of new projects was reported by WB in nine (9)
out of its 26 ongoing projects: Social Expenditure Management
Project II, LGU Urban Water, Agrarian Reform Communities Development
Project II, ARMM Social Fund, KALAHI, Judicial Reform, LISCOP,
Rural Power and Diversified Farms. There is also a need to strengthen
projects readiness filters to support quality-at-entry
of new projects. GOP, especially oversight agencies, should ensure
that adequate preparation has been undertaken prior to loan signing
such that agencies can undertake significant project scope immediately
at start - up.
116.
Where co-financing arrangements exist, harmonize procurement and
disbursement guidelines. Some projects are co-financed by two
or more funding institutions with distinct set of procurement
and disbursement guidelines. Harmonizing these guidelines as early
as project start-up would help ensure smooth project implementation.
117.
For sector/program loans, consider more reasonable sizes of loans
and broader scope to minimize partial cancellations and payment
of unnecessary commitment fees; strengthen project preparation
to firmup credit demand and pipeline of projects. Due to
over-estimated project cost and loan amounts, some projects have
requested partial cancellations.
118.
Address structure/staffing of PMOs in respective agency rationalization
pursuant to EO 366. The EO aims to attain improved government
performance, institute reforms that would transform the bureaucracy
into an efficient and results-oriented structure.
119.
Simplify rules and regulations and reduce reportorial requirements
in government transactions to conform with EO 428. The EO aims
to eliminate duplication and unnecessary requirements from business
and industry, thereby allowing them to devote maximum effort and
time to operation and expansion rather than comply with bureaucratic
requirements. An example is in the processing of billings of contractors,
where in one case, 15 steps/activities are required before payments
are made.
120.
In 2004, the DBM together with DOF and COA started the review
of Joint Circular No. 2-97 which provides guidelines for foreign-assisted
projects implemented by NG agencies and GOCCs. Proposed amendments
include the following : a) incorporate the procedure for charging/accounting
commitment fees under the agency ceilings, as approved by the
ICC; b) include guidelines on components of projects eligible
for forex payments; c) define acceptable implementation periods,
since extended implementation periods increase project costs;
d) efficient use of special accounts; and e) incentives for IAs
for cost-efficiency.
121.
On Budget - Review experience of RA 8150, otherwise known as the
Public Works and Highways Infrastructure Program Act of 1995 which
provided for a Four-Year Public Works and Highways Infrastructure
Program towards ensuring full and continuous multiyear budget
support to priority projects.
122.
Continue to explore budget-support type of loans for other NG
agencies. DepEd and DA are implementing the Social Expenditure
Management Program and the Diversified Farm Income and Market
Development Project. In this type of loans, agencies have better
management of the project as loans funds can be used to support
core functions of an agency.
123.
Pursue JBIC portfolio clean-up as agreed with the Japanese government
during the RP-Japan Dialogue in November 2004 by: a) reviewing
consistency of the projects with the MTPDP and MTPIP; and b) ensuring
full budget cover for ongoing projects, and where
this is not possible, to consider scaling down and partial/full
cancellation of loans for projects, such that all remaining projects,
after the clean-up will have full budget cover. Initial
review shows that: a) agencies with no budget cover issue are
all GOCCs/GFIs, DA, DLR, DOT, DENR, DepEd, NIA, PCSD, ARMM-SF
and PGNS; agency with budget cover risk is DPWH; and agencies
with budget cover issue are DILG, DOTC, and PGLDN (MIRIDP).
124.
On procurement of contracts, IAs should: a) share lessons learned
and good practices in procurement; b) shorten and reduce required
number of signatures for procurement and other transactions; c)
consider higher threshold for international competitive bidding
in order that more national competitive bidding will be undertaken;
d) look more deeply into cases of high bids (bids way above agency
estimates); and e) document experiences in JBIC Special Yen Loans.
125.
On the MDFO/MFC issue, DBM and MDFO to jointly prescribe appropriate
mode of release of NG grant to LGUs for ongoing projects; alternatively,
IAs to consider amending loan agreements on MDFO as conduit.
126.
On LGU Participation, IAs should synchronize project cycles with
the local elections such that key activities like sub-project
approvals and relocation are done before election years. More
important, ensure high quality of projects so that the probability
of continuing them and acceptance by the succeeding officials
is high.
H. BUDGET OUTLAY AND REQUIREMENTS (Table 10)
127.
Budget requirements of ongoing FAPs for succeeding years, as submitted
by agencies are as follows: about P42 billion for CY 2005, P56
billion for 2006, P39 billion for CY 2007, P20 billion for CY
2008, and P9 billion for CY 2009 and P4 billion for 2010 onwards.
I.
PROSPECTS IN 2005
128.
With the MTPDP and MTPIP now in place, the budgetary requirements
of FAPs are expected to be fully supported and implementation
will proceed as scheduled. In this regard, a mechanism for setting
realistic disbursement targets should be put in place at the start
of the year to have firmer basis for planning project implementation.
129.
Most projects of GOCCs with delayed procurement have been resolved.
Under the BCDA Subic- Clark-Tarlac Expressway Project, the Notices
to Proceed (NTPs) for the P21 billion civil works contract were
issued to the contractors on 21 March 2005; actual start of construction
is scheduled in April 2005. For the Northern Negros Geothermal
Project of PNOC-EDC, the NTP for the P3.7 billion 40 MW Power
Plant contract was issued to the contractor on 3 March 2005. In
LRTAs LRT Line 1 Capacity Expansion Project Phase II- Package
A, the contract amounting to P6.2 billion was awarded in December
2004 and NTP was issued on 15 March 2005. It is expected that
these big projects will pull-up the GOCCs performance indicators
in 2005.
130.
For CY 2005 , the GAA loan proceeds for FAPs (P26.672 billion)
if fully disbursed translates to only US$493 million, which is
17% lower than the 2004 actual disbursement of US$594 million,
excluding carry over budgets from 2004.
131.
The JBIC portfolio clean- up is expected to be completed by July
2005. The desired outcome is that budget constraints affecting
the portfolio will no longer be an issue after the clean up
until completion of the projects.
132.
Possible Cancellations in 2005 Partial and full cancellations
of about US$327million dollars from 16 projects are foreseen in
CY 2005, as a result of reduction in scope, unutilized loan balance,
budget constraints, and foreign exchange movement.
-----------------------------------------------------------------
[1]
Organisation for Economic Co-operation and Development (OECD)
defines ODA as flows of official financing administered with the
promotion of the economic development and welfare of developing
countries as the main objective, and which are concessional in
character with a grant element of at least 25 percent (using a
fixed 10 percent rate of discount)