July-September 2002
|
|||||||||||
| N | PROJECT/3rd Quarter Targets |
Accomplishments vs. Targets
|
PDMF Assistance | STATUS/ACCOMPLISHMENTS | DISBURSEMENTS (millions) | ||||||
| R | 3Q Target | 3Q Actual | % of Target | TOTAL TO DATE | % of Total | ||||||
| O | (million) | ||||||||||
| CAR | Master Plan for Cordillera Prime Education | 0.396 | STATUS: Finalization of Master Plan moved to October due to workload of | 0.028 | - | 0% | 0.337 | 85% | |||
| Center | TWG members. | ||||||||||
| > | Finalize and adopt Prime Education Master Plan | ||||||||||
| Master Plan for Alternative Transport System | 0.396 | STATUS: Minor delays incurred in accomplishing targets, but project is still | 0.095 | 0.011 | 11% | 0.108 | 27% | ||||
| forthe Cordillera | expected to be completed in December as planned. | ||||||||||
| > | Situation Analysis completed | > Situational Report completed in September instead of May. Delay was due to difficulties in | |||||||||
| gathering data and time constraints. | |||||||||||
| > | Draft Investment Plan prepared | > Vision, goal and objectives drafted. Development strategies were drafted | |||||||||
| by DOTC in coordination with NEDA TWG members. These will be presented | |||||||||||
| for consultation/critique and approval of the Infra SECOM next quarter. | |||||||||||
| SUBTOTAL | 0.792 | 0.123 | 0.011 | 9% | 0.445 | 56% | |||||
| I | Anda Island Development Master Plan | 0.500 | STATUS: Inception and Situational Reports completed, following dialogues | 0.500 | 0.025 | 5% | 0.100 | 20% | |||
| and workshops with various barangays. Completion of the Plan was moved | |||||||||||
| > | Final output completed | to 4th quarter. | |||||||||
| FS on CUMILOS Market Complex | 0.250 | STATUS: Marketing analysis submitted. Completion of FS moved to 4th | 0.250 | - | 0% | 0.038 | 15% | ||||
| quarter after the DILG and the consulting firm asked for a 1-month | |||||||||||
| > | Final output completed | extension. | |||||||||
| FS on Aloragat River Basin Watershed | 0.396 | STATUS: Draft of the study was presented to NRO I and DENR on July | 0.396 | - | 0% | 0.218 | 55% | 0.0792 | |||
| 2002. Comments are being incorporated to the draft. | 0.0594 | ||||||||||
| > | FS finalized | 0.1386 | |||||||||
| SUBTOTAL | 1.146 | 1.146 | 0.025 | 2% | 0.355 | 31% | |||||
| II | FS on Batanes Integrated Fisheries and Marine | 0.322 | STATUS: Inception Report was submitted to and reviewed by the NRO. | 0.097 | 0.097 | 100% | 0.145 | 45% | |||
| Resoures Development -- Batanes Marine Fisheries | Comments were forwarded to the contractor and the provincial government | ||||||||||
| Productivity Enhancement Program | for integration. Draft FS to be submitted in October. | ||||||||||
| > | Review and analysis of available data conducted; data gaps | Partial accomplishment of data gathering activities and market planning was | |||||||||
| identified. | achieved during the period. The delay was due to the postponement of the | ||||||||||
| > | Market Plan completed | consultant's trip to Batanes for the data gathering activities.However, activities | |||||||||
| > | Start activities on determining technical aspects | scheduled for 4th quarter (determining operational feasibility, report writing) | |||||||||
| have already started. | |||||||||||
| Local Government Economic Enterprise Development | 0.301 | Only 3 out of the 11 outputs were submitted by participant-LGUs despite | - | - | 0% | 0.291 | 97% | ||||
| (LEED) | several extension of deadlines. The final field interviews with participants | ||||||||||
| > | 11 well-prepared Pre-FS submitted | to elicit issues and recommendations on program improvement was | |||||||||
| > | Final field validation conducted | rescheduled fo next quarter. Findings will form part of the Terminal Report. | |||||||||
| > | Terminal Report prepared | ||||||||||
| FS on Sta. Fe Native Poultry Broodstock | 0.081 | STATUS: Mobilization fund was released to the LGU in September, after | 0.015 | 0.015 | 100% | 0.015 | 19% | ||||
| Development and Marketing | completion of the Contract Agreement between the LGU and the consultant | ||||||||||
| (Nueva Vizcaya State Institute of Technology). | |||||||||||
| > | Data gathering activities started | ||||||||||
| > | Inception Report prepared | Data gathering, market analysis and planning ongoing. | |||||||||
| > | Market analysis and planning started | ||||||||||
| FS on Production Alternatives for Cattle in | 0.081 | STATUS: Mobilization fund was released to the LGU in September, after | 0.015 | 0.015 | 100% | 0.015 | 19% | ||||
| Upland Areas, Sta. Fe, Nueva Viscaya | completion of the Contract Agreement between the LGU and the consultant | ||||||||||
| (Nueva Vizcaya State Institute of Technology). | |||||||||||
| > | Data gathering activities started | ||||||||||
| > | Inception Report prepared | Data gathering, market analysis and planning ongoing. | |||||||||
| > | Market analysis and planning started | ||||||||||
| FS on the Sto. Tomas Public Market | 0.105 | STATUS: Contract Agreement perfected; mobilization fund released in | 0.021 | 0.021 | 100% | 0.021 | 20% | ||||
| August. Project teams of LGU and contractor were also organized. However, | |||||||||||
| > | Contract Agreement signed | activities were slowed down because the LGU has not provided its | |||||||||
| > | Project Team formed | counterpart funds and manpower assistance. A tripartite meeting was held | |||||||||
| > | Data gaps identified and filled up | on Sept. 26 but the municipal mayor was absent. Another meeting was | |||||||||
| > | Inception Report prepared | scheduled in October to finally resolve the issue. | |||||||||
| > | Activities started on (a) Market Analysis and Planning; | ||||||||||
| (b) Structure design and specifications; (c) financial | Inception Report completed. Scheduled activities were in progress, except for | ||||||||||
| feasibility; and (d) operational feasibility | analysis of financial aspect and technical design. | ||||||||||
| SUBTOTAL | 0.890 | 0.148 | 0.148 | 100% | 0.487 | 55% | |||||
| III | Pre-FS on Ylang-ylang Essential Oil Livelihood | 0.201 | STATUS: Pre-FS completed 1st week of July. The study was formally | - | - | - | 0.201 | 100% | |||
| Project (Anao, Tarlac) | turned-over to the LGU during a simple ceremony on Sept. 27. The PFS | ||||||||||
| recommended a possible tie between the LGU and the Tarlac College of | |||||||||||
| > | Final Pre-FS completed | Agriculture which is planning to put up an ylang-ylang plantation. | |||||||||
| Master Development Plan for Licab, Nueva Ecija | 0.240 | STATUS: Master Plan completed 4th week of September. | 0.064 | 0.064 | 100% | 0.232 | 97% | ||||
| > | Master Plan completed | ||||||||||
| Pre-FS on the Rehabilitation/Improvement o fthe Llanera | 0.286 | STATUS: Completed 2nd quarter. | - | - | - | 0.286 | 100% | ||||
| Water System and Administration (Nueva Ecija) | |||||||||||
| Capability Building on Project Development for Selected | 0.137 | STATUS: Completed 1st quarter 2002 | - | - | - | 0.137 | 100% | ||||
| 4th to 6th Class LGUs in Region III | |||||||||||
| SUBTOTAL | 0.864 | 0.064 | 0.064 | 100% | 0.856 | 99% | |||||
| IV | REINA Master Planning and Project Pre-Feasibility | 0.700 | STATUS: The Plan was submitted in August and is being finalized by | 0.350 | 0.350 | 100% | 0.490 | 70% | |||
| Preparation | the consultants. The NRO approved a one-month extension due to frequent | ||||||||||
| power outages in the area. Final Pre-FS of two targeted projects were | |||||||||||
| > | Final Development Framework Plan submitted | completed in September. | |||||||||
| > | Final Pre-FS completed | ||||||||||
| a. REINA Coco Oil Mill Project | At the request of the LGU, the Terms of Reference of a hydro power project | ||||||||||
| b. REINA Aquaculture Seed Production Project | was also completed over and above the Master Plan and Pre-FS and | ||||||||||
| submitted in September. | |||||||||||
| Lubang Island Strategic Development Framework Plan | 0.400 | STATUS: The Draft Development Framework Plan and the Priority | 0.104 | - | 0% | 0.121 | 30% | ||||
| and Feasibility Studies Preparation | Investment Plan are being revised. Both drafts were submitted to the NRO | ||||||||||
| and the LGUs in August. | |||||||||||
| > | Draft Strategic Development Framework submitted | ||||||||||
| > | Draft Priority Investment Plan submitted | ||||||||||
| Pre-FS on Magdiwang Mountaineering Facilities Project | 0.240 | STATUS: Project completed 1st quarter (March). | - | - | - | 0.240 | 100% | 240 | |||
| SUBTOTAL | 1.340 | 0.454 | 0.350 | 77% | 0.851 | 64% | |||||
| V | FS on Guinobatan Solid Waste Management | 0.345 | STATUS: The LGU did not submit an accomplishment report for the period. | - | - | - | 0.195 | 57% | 209400 | ||
| FS is supposed to be completed this quarter. | |||||||||||
| > | Final FS completed | ||||||||||
| Phase I of FS on Polangui Upland Resources and | 0.538 | STATUS: Phase I of FS completed. | 0.412 | 0.412 | 100% | 0.538 | 100% | 412000 | |||
| Environmental (PURE) Project: SEPP Formulation, | |||||||||||
| Problem Analysis and Project Identification | |||||||||||
| > | Final report completed | ||||||||||
| Pre-FS on Baao Upland Resources | 0.524 | STATUS: Final Pre-FS not yet submitted by the LGU. | 0.524 | 0.430 | 82% | 0.430 | 82% | 328930 | |||
| Development Project | |||||||||||
| > | Pre-FS completed | ||||||||||
| SUBTOTAL | 1.407 | 0.936 | 0.842 | 90% | 1.163 | 83% | |||||
| VI | Pre-FS on Water Supply Development for Municipality of | 0.261 | STATUS: Drafting of FS is ongoing. theLGU was required to submit | 0.078 | - | 0% | 0.182 | 70% | 234000 | ||
| Altavas, Aklan | additional data to complete the FS after the 3-day writeshop to speed up | ||||||||||
| project completion was conducted in Septermber. | |||||||||||
| > | FS completed | ||||||||||
| Pre-FS on Construction of Public Market Building and | 0.293 | STATUS: Draft FS submitted 1st week of September; review of NRO VI | 0.090 | 0.060 | 67% | 0.269 | 92% | 270000 | |||
| Stalls in the Municipality of Buruanga, Aklan | ongoing. The project was earlier scheduled for completion in July. | ||||||||||
| > | Finalize Pre-FS | ||||||||||
| FS on Establishment of Post-Harvest Handling and | 0.281 | STATUS: FS completed and accepted by the LGU 4th week of September | 0.028 | 0.028 | 100% | 0.280 | 100% | 252000 | |||
| Processing Center in Municipality of Sigma, Capiz | (original schedule was July). | ||||||||||
| > | Final FS accepted | ||||||||||
| FS on Integrated Livelihood for Marginalized Fishfolk in | 0.201 | STATUS: FS not yet finalized. A draft was submitted in August but has not | 0.054 | 0.036 | 67% | 0.164 | 81% | 162000 | |||
| the Municipality of Tangalan, Aklan | been presented to stakeholders, thus the delay. | ||||||||||
| > | Final FS accepted | ||||||||||
| Pre-FS on Development of Suhot Spring Resort | 0.351 | STATUS:Pre-FS completed 4th week of July. | 0.105 | 0.105 | 100% | 0.350 | 100% | 315000 | |||
| > | Finalize Pre-FS | ||||||||||
| SUBTOTAL | 1.387 | 0.355 | 0.229 | 65% | 1.245 | 90% | |||||
| LUMP SUM FUND PROJECTS | |||||||||||
| Pre-FS on Agricultural Water Supply Improvement for | 0.400 | Both projects were approved on 26 July 2002 under the PDMF Lump Sum | - | - | - | - | - | 315000 | |||
| Ajuy, Iloilo | Fund, but funds have not been released yet. Monitoring of activities will start | ||||||||||
| next quarter. | |||||||||||
| Pre-FS on Project Packaging for Agriculture and Tourism | 0.394 | - | - | - | - | - | 315000 | ||||
| Development in Western Visayas | |||||||||||
| SUBTOTAL | 0.794 | 0.000 | 0.000 | - | 0.000 | - | |||||
| VII | FS on Construction of Roll On-Roll Off (RO-RO) Ports | 1.187 | STATUS: Contract with consultant TCGI Engineers signed on 27 August. The | 0.416 | 0.180 | 43% | 0.180 | 15% | |||
| contract amount of the project is One Million Pesos.Inception Report was | |||||||||||
| > | MOA for consulting services signed | approved in September. Data gathering activities for the preparation of the | |||||||||
| > | Inception Report prepared | situational analysis is ongoing. | |||||||||
| The NRO organized a Technical Committee to supervise, monitor and | |||||||||||
| coordinate the implementation of the study. It was also tasked to review and | |||||||||||
| recommend approval of all project reports. | |||||||||||
| SUBTOTAL | 1.187 | 0.416 | 0.180 | 0% | 0.180 | 15% | |||||
| VIII | FS on Guian (Sulangan) NatureTourism Destination | 0.497 | STATUS: Project completed 4th quarter of 2001 | - | - | -- | 0.497 | 100% | 496500 | ||
| FS on Jackfruit and Banana Production | 0.240 | STATUS: FS completed 1st quarter. | - | - | -- | 0.240 | 100% | 240000 | |||
| FS on Seaweeds and Lapu-lapu Production | 0.240 | STATUS: Project completed 4th quarter of 2001 | - | - | -- | 0.240 | 100% | ||||
| Project Identification thru Local Poverty Alleviation Plan | 0.179 | STATUS: Completed 2nd quarter | - | - | - | 0.179 | 100% | 151800 | |||
| (LPAP) Formulation | 136000 | ||||||||||
| SUBTOTAL | 1.156 | 0.000 | 0.000 | - | 1.156 | 100% | |||||
| IX | EGGA on ZN-PAIC Project | 0.300 | STATUS: Draft Final Report was submitted in August to the Mines and | - | - | - | 0.060 | 20% | |||
| Geosciences Bureau-Region IX for comments. The Provincial Government | |||||||||||
| > | Draft Report prepared | likewise forwarded its comments to the consultant for integration to the final | |||||||||
| > | EGG Report finalized and accepted | report before final payment is made. | |||||||||
| FS on the Proposed Rural Roads and Bridges | 0.350 | STATUS: The Sibugay Valley Project Management Office did not submit its | - | - | - | 0.132 | 38% | ||||
| Improvement Project and Proposed Barangay Water | accomplishment and financial report for 3rd quarter. | ||||||||||
| Su | |||||||||||
| PDAC-NRO IX is assisting Sibugay in the scheduled Integration Workshop in | |||||||||||
| > | Progress Report submitted | November. The workshop aims to integrate the Municipal Project Profiles | |||||||||
| > | Draft Report prepared | and studies into two feasibility study outputs, I.e., Roads and Water Supply. | |||||||||
| > | FS finalized and accepted | ||||||||||
| Zamboanga Peninsula Special Development Program | 0.382 | STATUS: ZamPen SDP was approved and endorsed by the RDC in its | - | - | - | 0.350 | 92% | ||||
| meeting n August, subject to some revisions. Final presentation to the RDC | |||||||||||
| > | ZamPen SDP finalized and accepted | is scheduled in December 3. A financial report shall be submitted after said | |||||||||
| date. | |||||||||||
| SUBTOTAL | 1.032 | 0.000 | 0.000 | - | 0.542 | 53% | |||||
| X | FS on the Proposed Municipal Waterworks Improvement/ | 1.075 | STATUS: FS on the Medina Municipal Waterworks was completed. The FS | - | - | - | 1.075 | 100% | |||
| Expansion Projects for Six (6) Municipalities: | on the improvement of the Dangcagan Municipal Waterworks is 85% | ||||||||||
| (1) Dangcagan, Bukidnon; (2) Pangantucan, Bukidnon; | completed. | ||||||||||
| (3) Kadingilan,Bukidnon; (4) Panaon,Mis. Occidental; (5) | |||||||||||
| Sinacaban, Mis.Occidental; (6) Medina,Misamis Or. | As the contract of services of two project staff were already completed at | ||||||||||
| the start of the 2nd quarter, the NRO staff carried on with the work. The tasks | |||||||||||
| > | Finalize FS Reports for Medina and Dangcagan | were over and above their regular work. | |||||||||
| SUBTOTAL | 1.075 | 0.000 | 0.000 | 0% | 1.075 | 100% | |||||
| XI | FS on Upland Irrigation Project for San Isidro, | 0.645 | STATUS: Completion of FS moved to 1st quarter of 2003 to validate and firm | - | - | - | 0.617 | 96% | ######## | ||
| Davao Oriental | up data on the pre-engineering aspects of the study. This may entail the | ||||||||||
| hiring of a local expert to conduct a technical survey of the project area. The | |||||||||||
| > | FS Report finalized | delay was partly due to the failure of the local government to provide the | |||||||||
| > | Fund source for the project identified | required personnel for the study. | |||||||||
| As part of its fund sourcing activities, the NRO XI provided information about | |||||||||||
| the project to Congressman Mayo Almario, when the latter inquired about the | |||||||||||
| project after reading a press release. A copy of the FS shall be furnished his | |||||||||||
| office once it is finalized. | |||||||||||
| FS on Infrastructure Support to the Economic Program of | 0.595 | STATUS: FS completed after a fouth-month consultation, validation and final | - | - | - | 0.587 | 99% | 54550.83 | |||
| Municipality of Sarangani, Davao del Sur | activities. | ||||||||||
| > | FS Report finalized | A breakthrough was gained in July when President Arroyo issued a | |||||||||
| > | Fund source for the project identified | memorandum to the DOTCand the Philippine Ports Authority to allocatefunds | |||||||||
| for the project. PPA has visited Sarangani in response to the President's | |||||||||||
| directive. The NRO will continue to follow through on the matter; PPA and | |||||||||||
| DOTC will be provided copies of the FS. | |||||||||||
| SUBTOTAL | 1.240 | 0.000 | 0.000 | - | 1.204 | 97% | |||||
| XII | FS on the Rehabilitation and Expansion of Water Supply | 0.100 | STATUS: Groundwork continued during the period, which | - | - | - | - | - | |||
| System-Level II in Libungan, Cotabato | culminated with the signing of the following agreements: | ||||||||||
| (a) MOU between the PDMF Coordination and Management Team (PCMT) | |||||||||||
| FS on Construction of Water Supply System Level II in | 0.280 | and the four (4) LGU-beneficiaries on the availment of PDMF assistance | |||||||||
| Arakan, Cotabato | |||||||||||
| (b) MOA between PDAC and the four LGU-beneficiaries for PDAC to handle | |||||||||||
| FS on Construction of Water Supply system-Level II in | 0.530 | the FS preparation of their respective project proposals signed on 2 Sept. 2002 | |||||||||
| Antipas, Cotabato | |||||||||||
| The Notice to Proceed released on 24 September marked the official take off | |||||||||||
| FS on Construction/Expansion of WaterSystem Level II in | 0.180 | of all four projects.Projects are expected to be in full swing next quarter. | |||||||||
| Aleosan, Cotabato | |||||||||||
| SUBTOTAL | 1.090 | 0.000 | 0.000 | 0% | 0.000 | 0% | |||||
| XIII | FS on Establishment of Municipal Grains Center in Sta. | 0.160 | STATUS: FS completed in May. | - | - | - | 0.160 | 100% | |||
| Josefa, Agusan del Sur | |||||||||||
| > | Finalize FS | ||||||||||
| Cluster Capability Building Program on Project | 0.564 | STATUS: Eleven out of 12 LGUs submitted their Pre-FS outputs. The | 0.056 | - | 0% | 0.508 | 90% | ||||
| Development for 4th to 6th Class Municipalities in | participants had difficulty completing the outputs despite continous coaching | ||||||||||
| Surigao del Norte | and monitoring by the Provincial Government.This was caused partly by the | ||||||||||
| workload of LGU representatives and the inavailability of data. | |||||||||||
| > | Project Proposals and Pre-FS finalized | ||||||||||
| FS on the Establishment of a Farm Level Grain Center in | 0.160 | STATUS: Project activities accomplished as planned. The Inception Report | 0.048 | - | 0% | 0.048 | 30% | ||||
| Jabonga, Agusan del Norte | was submitted in September. However, the LGU has not submitted the | ||||||||||
| audited financial report, thereby delaying release of the second and third | |||||||||||
| > | Project contracted | tranches. | |||||||||
| > | Inception Report prepared | ||||||||||
| > | Draft FS submitted | ||||||||||
| SUBTOTAL | 0.884 | 0.104 | 0.000 | 0% | 0.716 | 81% | |||||
| LUMP SUM PROJECT | |||||||||||
| FS on the Establishment of a Farm Level Grain Center in | 0.160 | The project was approved on 30 July 2002 under the PDMF Lump Sum | - | - | - | - | - | ||||
| Prosperidad, Agusan del Sur | Fund, but funds have not been released as of this quarter. Monitoring of | ||||||||||
| activities will start next quarter. The project is part of the GOP-AECI Program | |||||||||||
| on Improve Food Sufficiency in Caraga Region. | |||||||||||
| SUBTOTAL | 0.160 | 0.000 | 0.000 | - | 0.000 | - | |||||
| GRAND TOTAL | 16.445 | 3.746 | 1.848 | 49% | 10.274 | 62% | |||||