July-September 2002
N   PROJECT/3rd Quarter Targets
Accomplishments vs. Targets
PDMF Assistance STATUS/ACCOMPLISHMENTS DISBURSEMENTS (millions)        
R    3Q Target  3Q Actual % of Target  TOTAL TO DATE % of Total
O       (million)            
             
CAR Master Plan for Cordillera Prime Education 0.396 STATUS: Finalization of Master Plan moved to October due to workload of   0.028          -   0%           0.337 85%  
  Center   TWG members.          
             
  > Finalize and adopt Prime Education Master Plan              
             
  Master Plan for Alternative Transport System 0.396 STATUS: Minor delays incurred in accomplishing targets, but project is still   0.095   0.011 11%           0.108 27%
  forthe Cordillera   expected to be completed in December as planned.          
             
  > Situation Analysis completed   > Situational Report completed in September instead of May. Delay was due to difficulties in          
    gathering data and time constraints.          
  > Draft Investment Plan prepared   > Vision, goal and objectives drafted. Development strategies were drafted          
    by DOTC in coordination with NEDA TWG members. These will be presented          
     for consultation/critique and approval of the Infra SECOM next quarter.          
             
    SUBTOTAL 0.792   0.123 0.011 9% 0.445 56%
             
I Anda Island Development Master Plan 0.500 STATUS: Inception and Situational Reports completed, following dialogues   0.500   0.025 5%           0.100 20%
    and workshops with various barangays. Completion of the Plan was moved          
  > Final output completed   to 4th quarter.          
             
  FS on CUMILOS Market Complex 0.250 STATUS: Marketing analysis submitted. Completion of FS moved to 4th   0.250          -   0%           0.038 15%
    quarter after the DILG and the consulting firm asked for a 1-month          
  > Final output completed   extension.          
             
  FS on Aloragat River Basin Watershed 0.396 STATUS: Draft of the study was presented to NRO I and DENR on July   0.396          -   0%           0.218 55% 0.0792
      2002. Comments are being incorporated to the draft.           0.0594
  > FS finalized             0.1386
             
    SUBTOTAL 1.146   1.146 0.025 2% 0.355 31%
             
II FS on Batanes Integrated Fisheries and Marine 0.322 STATUS: Inception Report was submitted to and reviewed by the NRO. 0.097   0.097 100%           0.145 45%
  Resoures Development -- Batanes Marine Fisheries   Comments were forwarded to the contractor and the provincial government          
  Productivity Enhancement Program   for integration. Draft FS to be submitted in October.          
             
  > Review and analysis of available data conducted; data gaps   Partial accomplishment of data gathering activities and market planning was          
  identified.   achieved during the period. The delay was due to the postponement of the          
  > Market Plan completed   consultant's trip to Batanes for the data gathering activities.However, activities          
  > Start activities on determining technical aspects   scheduled for 4th quarter (determining operational feasibility, report writing)          
          have already started.          
             
  Local Government Economic Enterprise Development 0.301 Only 3 out of the 11 outputs were submitted by participant-LGUs despite          -            -   0%           0.291 97%
  (LEED)   several extension of deadlines. The final field interviews with participants          
  > 11 well-prepared Pre-FS submitted   to elicit issues and recommendations on program improvement was          
  > Final field validation conducted   rescheduled fo next quarter. Findings will form part of the Terminal Report.          
  > Terminal Report prepared            
                     
  FS on Sta. Fe Native Poultry Broodstock 0.081 STATUS: Mobilization fund was released to the LGU in September, after   0.015   0.015 100%           0.015 19%
  Development and Marketing   completion of the Contract Agreement between the LGU and the consultant          
    (Nueva Vizcaya State Institute of Technology).          
  > Data gathering activities started            
  > Inception Report prepared   Data gathering, market analysis and planning ongoing.          
  > Market analysis and planning started              
             
  FS on Production Alternatives for Cattle in 0.081 STATUS: Mobilization fund was released to the LGU in September, after   0.015   0.015 100%           0.015 19%
  Upland Areas, Sta. Fe, Nueva Viscaya   completion of the Contract Agreement between the LGU and the consultant          
    (Nueva Vizcaya State Institute of Technology).          
  > Data gathering activities started            
  > Inception Report prepared   Data gathering, market analysis and planning ongoing.          
  > Market analysis and planning started              
             
  FS on the Sto. Tomas Public Market 0.105 STATUS: Contract Agreement perfected; mobilization fund released in   0.021   0.021 100%           0.021 20%
    August. Project teams of LGU and contractor were also organized. However,          
  > Contract Agreement signed   activities were slowed down because the LGU has not provided its          
  > Project Team formed   counterpart funds and manpower assistance.  A tripartite meeting was held          
  > Data gaps identified and filled up   on Sept. 26 but the municipal mayor was absent. Another meeting was          
  > Inception Report prepared   scheduled in October to finally resolve the issue.          
  > Activities started on (a) Market Analysis and Planning;            
  (b) Structure design and specifications; (c) financial   Inception Report completed. Scheduled activities were in progress, except for          
  feasibility; and (d) operational feasibility   analysis of financial aspect and technical design.          
             
    SUBTOTAL 0.890   0.148 0.148 100% 0.487 55%
             
III Pre-FS on Ylang-ylang Essential Oil Livelihood 0.201 STATUS: Pre-FS completed 1st week of July. The study was formally          -            -   -           0.201 100%
  Project (Anao, Tarlac)   turned-over to the LGU during a simple ceremony on Sept. 27. The PFS          
    recommended a possible tie between the LGU and the Tarlac College of          
  > Final Pre-FS completed   Agriculture which is planning to put up an ylang-ylang plantation.          
             
  Master Development Plan for Licab, Nueva Ecija 0.240 STATUS: Master Plan completed 4th week of September.   0.064   0.064 100%           0.232 97%
  > Master Plan completed              
             
  Pre-FS on the Rehabilitation/Improvement o fthe Llanera 0.286 STATUS: Completed 2nd quarter.          -    - -           0.286 100%
  Water System and Administration (Nueva Ecija)              
             
  Capability Building on Project Development for Selected 0.137 STATUS: Completed 1st quarter 2002          -            -   -           0.137 100%
  4th to 6th Class LGUs in Region III              
               
    SUBTOTAL 0.864   0.064 0.064 100% 0.856 99%
             
IV REINA Master Planning and Project Pre-Feasibility 0.700 STATUS: The Plan was submitted in August and is being finalized by   0.350   0.350 100%           0.490 70%
  Preparation   the consultants. The NRO approved a one-month extension due to frequent          
    power outages in the area. Final Pre-FS of two targeted projects were          
  > Final Development Framework Plan submitted   completed in September.          
  > Final Pre-FS completed            
  a. REINA Coco Oil Mill Project   At the request of the LGU, the Terms of Reference of a hydro power project          
  b. REINA Aquaculture Seed Production Project   was also completed over and above the Master Plan and Pre-FS and          
        submitted in September.          
             
  Lubang Island Strategic Development Framework Plan 0.400 STATUS: The Draft Development Framework Plan and the Priority   0.104          -   0%           0.121 30%
  and Feasibility Studies Preparation   Investment Plan are being revised. Both drafts were submitted to the NRO          
    and the LGUs in August.          
  > Draft Strategic Development Framework submitted            
    > Draft Priority Investment Plan submitted              
             
  Pre-FS on Magdiwang Mountaineering Facilities Project 0.240 STATUS: Project completed 1st quarter (March).          -            -   -           0.240 100% 240
             
    SUBTOTAL 1.340   0.454 0.350 77% 0.851 64%
             
V FS on Guinobatan Solid Waste Management 0.345 STATUS: The LGU did not submit an accomplishment report for the period.  -  - -           0.195 57% 209400
    FS is supposed to be completed this quarter.          
  > Final FS completed            
                   
  Phase I of FS on Polangui Upland Resources and 0.538 STATUS: Phase I of FS completed.   0.412   0.412 100% 0.538 100% 412000
  Environmental (PURE) Project: SEPP Formulation,            
  Problem Analysis and Project Identification            
             
  > Final report completed            
                   
  Pre-FS on Baao Upland Resources 0.524 STATUS: Final Pre-FS not yet submitted by the LGU.   0.524   0.430 82%           0.430 82% 328930
  Development Project            
             
  > Pre-FS completed            
             
    SUBTOTAL 1.407   0.936 0.842 90% 1.163 83%
             
VI Pre-FS on Water Supply Development for Municipality of 0.261 STATUS: Drafting of FS is ongoing. theLGU was required to submit   0.078          -   0%           0.182 70% 234000
  Altavas, Aklan   additional data to complete the FS after the 3-day writeshop to speed up          
    project completion was conducted in Septermber.          
    > FS completed              
             
  Pre-FS on Construction of Public Market Building and 0.293 STATUS: Draft FS submitted 1st week of September; review of NRO VI   0.090   0.060 67%           0.269 92% 270000
  Stalls in the Municipality of Buruanga, Aklan   ongoing. The project was earlier scheduled for completion in July.          
             
  > Finalize Pre-FS              
             
  FS on Establishment of Post-Harvest Handling and 0.281 STATUS: FS completed and accepted by the LGU 4th week of September   0.028   0.028 100%           0.280 100% 252000
  Processing Center in Municipality of Sigma, Capiz   (original schedule was July).          
             
    > Final FS accepted              
             
  FS on Integrated Livelihood for Marginalized Fishfolk in 0.201 STATUS: FS not yet finalized. A draft was submitted in August but has not   0.054   0.036 67%           0.164 81% 162000
  the Municipality of Tangalan, Aklan   been presented to stakeholders, thus the delay.          
             
  > Final FS accepted              
             
  Pre-FS on Development of Suhot Spring Resort 0.351 STATUS:Pre-FS completed 4th week of July.   0.105   0.105 100%           0.350 100% 315000
             
  > Finalize Pre-FS              
             
  SUBTOTAL 1.387   0.355 0.229 65% 1.245 90%
             
  LUMP SUM FUND PROJECTS            
  Pre-FS on Agricultural Water Supply Improvement for 0.400 Both projects were approved on 26 July 2002 under the PDMF Lump Sum          -            -   -                  -   - 315000
  Ajuy, Iloilo   Fund, but funds have not been released yet. Monitoring of activities will start          
        next quarter.          
             
  Pre-FS on Project Packaging for Agriculture and Tourism 0.394          -            -   -                  -   - 315000
  Development in Western Visayas            
             
  SUBTOTAL 0.794   0.000 0.000 - 0.000 -
                     
             
VII FS on Construction of Roll On-Roll Off (RO-RO) Ports 1.187 STATUS: Contract with consultant TCGI Engineers signed on 27 August. The   0.416   0.180 43%           0.180 15%
    contract amount of the project is One Million Pesos.Inception Report was          
  > MOA for consulting services signed   approved in September. Data gathering activities for the preparation of the          
  > Inception Report prepared   situational analysis is ongoing.          
             
    The NRO organized a Technical Committee to supervise, monitor and          
    coordinate the implementation of the study. It was also tasked to review and          
    recommend approval of all project reports.          
             
    SUBTOTAL 1.187   0.416 0.180 0% 0.180 15%
             
VIII FS on Guian (Sulangan) NatureTourism Destination 0.497 STATUS: Project completed 4th quarter of 2001          -            -   -- 0.497 100% 496500
             
  FS on Jackfruit and Banana Production 0.240 STATUS: FS completed 1st quarter.          -            -   --           0.240 100% 240000
             
  FS on Seaweeds and Lapu-lapu Production 0.240 STATUS: Project completed 4th quarter of 2001          -            -   --           0.240 100%
             
  Project Identification thru Local Poverty Alleviation Plan 0.179 STATUS:  Completed 2nd quarter          -            -   -           0.179 100% 151800
  (LPAP) Formulation             136000
             
    SUBTOTAL 1.156   0.000 0.000 - 1.156 100%
             
IX EGGA on ZN-PAIC Project 0.300 STATUS: Draft Final Report was submitted in August to the Mines and          -            -   -           0.060 20%
    Geosciences Bureau-Region IX for comments. The Provincial Government          
  > Draft Report prepared   likewise forwarded its comments to the consultant for integration to the final          
    > EGG Report finalized and accepted   report before final payment is made.          
             
  FS on the Proposed Rural Roads and Bridges 0.350 STATUS: The Sibugay Valley Project Management Office did not submit its  -  - -           0.132 38%
  Improvement Project and Proposed Barangay Water   accomplishment and financial report for 3rd quarter.          
  Supply Level II for Sibugay Valley            
    PDAC-NRO IX is assisting Sibugay in the scheduled Integration Workshop in          
  > Progress Report submitted   November. The workshop aims to integrate the Municipal Project Profiles          
  > Draft Report prepared   and studies into two feasibility study outputs, I.e., Roads and Water Supply.          
  > FS finalized and accepted              
             
  Zamboanga Peninsula Special Development Program 0.382 STATUS: ZamPen SDP was approved and endorsed by the RDC in its          -            -   -           0.350 92%
    meeting n August, subject to some revisions. Final presentation to the RDC          
  > ZamPen SDP finalized and accepted   is scheduled in December 3. A financial report shall be submitted after said          
    date.          
    SUBTOTAL 1.032   0.000 0.000 - 0.542 53%
             
X FS on the Proposed Municipal Waterworks Improvement/ 1.075 STATUS: FS on the Medina Municipal Waterworks was completed. The FS          -            -   - 1.075 100%
  Expansion Projects for Six (6) Municipalities:   on the improvement of the Dangcagan Municipal Waterworks is 85%          
  (1) Dangcagan, Bukidnon; (2) Pangantucan, Bukidnon;   completed.          
  (3) Kadingilan,Bukidnon; (4) Panaon,Mis. Occidental; (5)            
  Sinacaban, Mis.Occidental; (6) Medina,Misamis Or.   As the contract of services of two project staff were already completed at          
    the start of the 2nd quarter, the NRO staff carried on with the work. The tasks          
  > Finalize FS Reports for Medina and Dangcagan   were over and above their regular work.          
             
    SUBTOTAL 1.075   0.000 0.000 0% 1.075 100%
             
XI FS on Upland Irrigation Project for San Isidro, 0.645 STATUS: Completion of FS moved to 1st quarter of 2003 to validate and firm          -            -   -           0.617 96% ########
  Davao Oriental   up data on the pre-engineering aspects of the study. This may entail the          
    hiring of a local expert to conduct a technical survey of the project area. The          
  > FS Report finalized   delay was partly due to the failure of the local government to provide the          
  > Fund source for the project identified   required personnel for the study.           
             
    As part of its fund sourcing activities, the NRO XI provided information about          
    the project to Congressman Mayo Almario, when the latter inquired about the          
    project after reading a press release. A copy of the FS shall be furnished his          
        office once it is finalized.          
             
  FS on Infrastructure Support to the Economic Program of 0.595 STATUS: FS completed after a fouth-month consultation, validation and final          -            -   -           0.587 99% 54550.83
  Municipality of Sarangani, Davao del Sur   activities.          
             
  > FS Report finalized   A breakthrough was gained in July when President Arroyo issued a          
  > Fund source for the project identified   memorandum to the DOTCand the Philippine Ports Authority to allocatefunds          
    for the project. PPA has visited Sarangani in response to the President's          
    directive. The NRO will continue to follow through on the matter; PPA and          
    DOTC will be provided copies of the FS.          
             
    SUBTOTAL 1.240   0.000 0.000 - 1.204 97%
             
XII FS on the Rehabilitation and Expansion of Water Supply 0.100 STATUS: Groundwork continued during the period, which          -            -           -                    -           -  
  System-Level II in Libungan, Cotabato   culminated with the signing of the following agreements:          
    (a) MOU between the PDMF Coordination and Management Team (PCMT)          
  FS on Construction of Water Supply System Level II in 0.280 and the four (4) LGU-beneficiaries on the availment of PDMF assistance          
  Arakan, Cotabato            
    (b) MOA between PDAC and the four LGU-beneficiaries for PDAC to handle          
  FS on Construction of Water Supply system-Level II in 0.530 the FS preparation of their respective project proposals signed on 2 Sept. 2002          
  Antipas, Cotabato            
    The Notice to Proceed released on 24 September marked the official take off          
  FS on Construction/Expansion of WaterSystem Level II in 0.180 of all four projects.Projects are expected to be in full swing next quarter.          
  Aleosan, Cotabato            
             
    SUBTOTAL 1.090   0.000 0.000 0% 0.000 0%
             
XIII FS on Establishment of Municipal Grains Center in Sta. 0.160 STATUS: FS completed in May.          -            -   -           0.160 100%
  Josefa, Agusan del Sur            
  > Finalize FS              
             
  Cluster Capability Building Program on Project 0.564 STATUS: Eleven out of 12 LGUs submitted their Pre-FS outputs. The   0.056          -   0%           0.508 90%
  Development for 4th to 6th Class Municipalities in   participants had difficulty completing the outputs despite continous coaching          
  Surigao del Norte   and monitoring by the Provincial Government.This was caused partly by the          
    workload of LGU representatives and the inavailability of data.          
  > Project Proposals and Pre-FS finalized            
                   
             
  FS on the Establishment of a Farm Level Grain Center in 0.160 STATUS: Project activities accomplished as planned. The Inception Report   0.048          -   0%           0.048 30%
  Jabonga, Agusan del Norte   was submitted in September. However, the LGU has not submitted the          
    audited financial report, thereby delaying release of the second and third          
  > Project contracted   tranches.          
  > Inception Report prepared            
  > Draft FS submitted            
             
  SUBTOTAL 0.884   0.104 0.000 0% 0.716 81%
             
  LUMP SUM PROJECT            
  FS on the Establishment of a Farm Level Grain Center in 0.160 The project was approved on 30 July 2002 under the PDMF Lump Sum          -            -   -                  -   -
  Prosperidad, Agusan del Sur   Fund, but funds have not been released as of this quarter. Monitoring of          
    activities will start next quarter. The project is part of the GOP-AECI Program          
    on Improve Food Sufficiency in Caraga Region.          
             
  SUBTOTAL 0.160   0.000 0.000 - 0.000 -
                     
      GRAND TOTAL 16.445   3.746 1.848 49% 10.274 62%